Exam Question 651

One of the key project team members is assigned to two other projects. The project schedule shows this resource needed during the same time they’re needed on one of the other projects. What does this describe?

A. Resource allocation
B. Interproject resource contention
C. Resource shortage
D. Resource conflict
Correct Answer:
B. Interproject resource contention

Exam Question 652

You are working on your network diagram. Activity A is a predecessor to Activity B. Activity B cannot begin until Activity A is completed. What is this telling you?

A. There is a mandatory dependency between Activity A and Activity B.
B. There is a finish-to-start dependency relationship between Activity A and Activity B.
C. Activity A and Activity B are both on the critical path.
D. Activity B is a successor to multiple tasks.
Correct Answer:
B. There is a finish-to-start dependency relationship between Activity A and Activity B.

Exam Question 653

Which of the following is not a key component of scope planning?

A. Work breakdown structure (WBS)
B. Scope statement
C. Project charter
D. Scope management plan
Correct Answer:
C. Project charter

Exam Question 654

Which of the following helps to build an efficient and effective team, improves morale, and builds social bonds?

A. Team building
B. Trust building
C. Having dedicated resources on the project team
D. Using appropriate conflict-resolution techniques at the right time
Correct Answer:
A. Team building

Exam Question 655

Which of the following does not describe a constraint?

A. Project team actions are dictated.
B. It may regard budget, resources, or schedule.
C. Project team actions are restricted.
D. Project situations are believed to be true.
Correct Answer:
D. Project situations are believed to be true.

Exam Question 656

You are in the process of determining the cost baseline. All of the following are used in the cost baseline except for which one?

A. Management reserves
B. Chart of accounts
C. Human resource cost estimates
D. Materials and equipment estimates
Correct Answer:
A. Management reserves

Exam Question 657

All of the following are considered stakeholder communication requirements except for which one?

A. Frequency
B. Distribution of printed media
C. Confidentiality constraints
D. Tailor communication style to stakeholder needs
Correct Answer:
B. Distribution of printed media

Exam Question 658

You’re working on a project that you and your team have estimated takes 15 business days to complete. Your team does not work on Saturday, Sunday, or holidays. Given the work calendar shown here and a start date of Tuesday, November 1, what is the scheduled completion date for this task?

Given the work calendar shown here and a start date of Tuesday, November 1, what is the scheduled completion date for this task?

A. 21
B. 15
C. 22
D. 23
Correct Answer:
C. 22

Exam Question 659

Which element is not a component or function of the scope management plan?

A. Describes the deliverables acceptance criteria
B. Describes how scope changes will be handled
C. Describes the procedures for preparing the scope statement
D. Describes the procedures for preparing the WBS
Correct Answer:
A. Describes the deliverables acceptance criteria

Exam Question 660

You are a project manager for a major movie studio. You need to schedule a shoot in Denver during ski season. This is an example of which of the following?

A. External dependency
B. Finish-to-start relationship
C. Mandatory dependency
D. Discretionary dependency
Correct Answer:
A. External dependency