The latest CompTIA Project+ PK0-004 certification actual real practice exam question and answer (Q&A) dumps are available free, which are helpful for you to pass the CompTIA Project+ PK0-004 exam and earn CompTIA Project+ PK0-004 certification.
Exam Question 431
During a CCB, a SME evaluated the impact and provided new information because of business process changes for handling potential failure.
Which of the following documents should be updated?
A. Incident response
B. Project plan
C. Risk register
D. Business continuity plan
Correct Answer:
A. Incident response
Exam Question 432
The project team is moving from high-level risks to detailed risks.
Which of the following project phases is the project team moving between?
A. Execution to monitor and control
B. Initiation to planning
C. Initiation to monitor and control
D. Planning to execution
Correct Answer:
D. Planning to execution
Exam Question 433
Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3. Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day.
Which of the following represents the critical path?
A. Five days
B. Six days
C. Seven days
D. Eight days
Correct Answer:
B. Six days
Exam Question 434
A project team is working on a project with high public visibility and excitement. The project sponsor is concerned the public may lose interest due to the long delivery timeline.
Which of the following is the BEST way to keep the external stakeholders informed and engaged throughout the project?
A. Video conferencing
B. Instant messaging
C. Social media
D. Email
Correct Answer:
C. Social media
Exam Question 435
A project sponsor wants to know which tasks are next in the project but is unable to find this information.
Which of the following may need to be adjusted?
A. Scope document
B. Status report
C. Issue log
D. Risk log
Correct Answer:
B. Status report
Exam Question 436
Which of the following represents the order of the team development stages?
A. Forming, storming, norming, performing
B. Forming, performing, storming, norming
C. Forming, norming, storming, performing
D. Forming, norming, performing, storming
Correct Answer:
A. Forming, storming, norming, performing
Exam Question 437
A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change.
Which of the following is the MOST likely reason?
A. Established communication plan
B. Scope creep
C. Resource constraints
D. Iterative approach
Correct Answer:
B. Scope creep
Exam Question 438
Rather than sending emails to communicate all project information, the project manager:
Makes telephone calls to key stakeholders for urgent information
Sends emails for routine information
Posts on the project intranet site for required but minimally used information
Which of the following BEST represents what the project manager is doing?
A. Prioritizing based on personal preferences
B. Tailoring the method based on message content
C. Adjusting the method based on confidentiality constraints
D. Demonstrating concern for technological factors
Correct Answer:
B. Tailoring the method based on message content
Exam Question 439
A project team received a memo stating no one can come into the office for the rest of the week due to heavy forecasted rain. The projected team reviews the risk management plan and carries out the risk response.
The memo that prompted the activation of the risk response is referred to as the:
A. risk owner
B. risk impact
C. risk review
D. risk trigger
Correct Answer:
D. risk trigger
Exam Question 440
An employee is assigned to a project and is developing a project charter.
Which of the following are some of the constraints the employee would typically face at this stage of the project?
A. Environment, resources, requirements, and quality
B. Budget, quality, resources, and schedule
C. Deliverables, scope, and budget environment
D. Budget, scope, quality, and schedule
Correct Answer:
D. Budget, scope, quality, and schedule