The latest CompTIA Project+ PK0-004 certification actual real practice exam question and answer (Q&A) dumps are available free, which are helpful for you to pass the CompTIA Project+ PK0-004 exam and earn CompTIA Project+ PK0-004 certification.
Exam Question 691
What is considered the most accurate estimate?
A. Analogous estimate
B. Bottom-up estimate
C. Estimates based on expert judgment
D. Parametric estimate
Correct Answer:
B. Bottom-up estimate
Exam Question 692
Randy is a key technical resource for your project. You’ve worked with Randy on past projects and have identified him as one of the team members who will work on the project. The charter has been published, and there is great excitement about this project. You’ve scheduled a meeting to talk to Randy’s functional manager next week. Which of the following conditions does this describe?
A. Risk
B. Assumption
C. Deliverable
D. Constraint
Correct Answer:
B. Assumption
Exam Question 693
You are developing a bottom-up estimate for the first phase of your project. Which of the following is the most important input to complete this task?
A. Historic data from a similar project
B. Chart of accounts
C. The WBS
D. The scope statement
Correct Answer:
C. The WBS
Exam Question 694
What is the lowest level of the WBS?
A. Work package
B. Level 5
C. Milestone
D. Activities
Correct Answer:
A. Work package
Exam Question 695
What are the crashing and fast tracking techniques used for?
A. Duration compression
B. Activity sequencing
C. Precedence diagramming
D. Task definition
Correct Answer:
A. Duration compression
Exam Question 696
This entity is responsible for reviewing change requests, reviewing the analysis of the impact of the change, and determining whether the change is approved, denied, or deferred.
A. CAB
B. CCB
C. CRB
D. TRB
Correct Answer:
B. CCB
Exam Question 697
Starting two activities at the same time that were previously scheduled to start sequentially is known as which of the following?
A. Fast tracking
B. Mandatory dependency
C. Crashing
D. Baselining
Correct Answer:
A. Fast tracking
Exam Question 698
Which of the following charts is a type of histogram?
A. Scatter diagram
B. Fishbone
C. Pareto chart
D. Run chart
Correct Answer:
C. Pareto chart
Exam Question 699
Your project is in danger of being canceled because of an organizational change. Despite the protests of your executive manager, several of the department managers in your old company have been laid off and replaced by the new organization’s management team. Which of the following options does this scenario describe?
A. Your company has experienced a demerger from another organization.
B. Your company has been merged with another organization.
C. Your company has been acquired by another organization.
D. Your company has split from another organization.
Correct Answer:
C. Your company has been acquired by another organization.
Exam Question 700
Which of the following should be established as part of the change control system in the event the change control board (CCB) cannot meet in a timely manner?
A. Emergency change request procedures
B. Procedures for analyzing the impacts of change and preestablished criteria for determining which changes can be implemented
C. Process for documenting the change in the change request log
D. Coordination and communication with stakeholders
Correct Answer:
A. Emergency change request procedures