The latest CompTIA Project+ PK0-004 certification actual real practice exam question and answer (Q&A) dumps are available free, which are helpful for you to pass the CompTIA Project+ PK0-004 exam and earn CompTIA Project+ PK0-004 certification.
Exam Question 501
Which of the following project phases would MOST likely include creating a transition plan?
A. Closing
B. Initiation
C. Execution
D. Planning
Correct Answer:
D. Planning
Exam Question 502
A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered.
Which of the following are MOST likely missing from the project? (Choose two.)
A. Project charter
B. Organizational chart
C. Scope document
D. Status report
E. Business case
F. Project plan
Correct Answer:
C. Scope document
F. Project plan
Exam Question 503
As a project processes, the team appears disjointed. Meetings are not effective because the right team members are not in the discussion, and functional managers are questioning if the project manager has a true management plan.
Which of the following documents should be reviewed FIRST to uncover the issue?
A. Communications plan
B. Scope statement
C. Project management plan
D. Organizational chart
Correct Answer:
A. Communications plan
Exam Question 504
A project manager is reviewing documents to develop the project charter. While reviewing historical project documentation, the project manager decides to include the following in the charter:
- Project title description
- Preassigned resources
- Budget
- WBS
- Measurable project objectives
Which of the following components should be a part of the project management plan instead of the project charter?
A. Project title and description
B. Preassigned resources
C. Budget
D. WBS
E. Measurable project objectives
Correct Answer:
D. WBS
Exam Question 505
A project manager is determining a project’s critical path to report the projected completion date to stakeholders.
Which of the following information will be required? (Choose two.)
A. Costs
B. Dependencies
C. Schedules
D. Durations
E. Holidays
F. Milestones
Correct Answer:
B. Dependencies
D. Durations
Exam Question 506
Which of the following documents should the project manager complete if requirements have been defined, but neither a vendor nor a platform has been identified?
A. RFP
B. RFQ
C. RFI
D. SOW
Correct Answer:
A. RFP
Exam Question 507
Given the following sprint:
Which of the following charts BEST demonstrates the decreasing number of Not Started items for the sprint depicted above?
A. Gantt chart
B. Pareto chart
C. Scatter chart
D. Burndown chart
Correct Answer:
A. Gantt chart
Exam Question 508
The design team and development team disagree about what technology should be used for a major requirement. A brainstorming meeting takes place, where both teams focus on the mutually agreed-upon deliverables.
Which of the following conflict resolution techniques did the teams use?
A. Compromising
B. Smoothing
C. Confronting
D. Forcing
Correct Answer:
A. Compromising
Exam Question 509
The project manager needs to motivate the team; however, there is an insufficient budget for awards.
Which of the following motivating agents is the MOST appropriate option the project manager can utilize?
A. Reduce the workload
B. Replace resources
C. Extend the timeline
D. Provide additional responsibility
Correct Answer:
D. Provide additional responsibility
Exam Question 510
A PM is reviewing bids from vendors and has a question.
Which of the following documents should the PM use to obtain a response?
A. Project schedule
B. RFP
C. Quotation
D. RFI
Correct Answer:
B. RFP