The latest CompTIA Project+ PK0-004 certification actual real practice exam question and answer (Q&A) dumps are available free, which are helpful for you to pass the CompTIA Project+ PK0-004 exam and earn CompTIA Project+ PK0-004 certification.
Exam Question 541
A stakeholder is unaware of a project-s status.
Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)
A. Status report
B. Organizational chart
C. RACI matrix
D. Meeting minutes
E. Communication plan
Correct Answer:
A. Status report
D. Meeting minutes
Exam Question 542
A construction company is building a plant in a territory that is prone to earthquakes. To address the risk and consequences of potential earthquakes during and after plant construction, the company purchases additional insurance. Which of the following risk responses has occurred?
A. Avoiding
B. Mitigating
C. Accepting
D. Transferring
Correct Answer:
D. Transferring
Exam Question 543
Which of the following is the BEST reason to use a burndown chart?
A. To determine how much risk is still associated with the project
B. To predict when project work will be completed
C. To establish a backlog for project deliverables
D. To create a project charter
Correct Answer:
B. To predict when project work will be completed
Exam Question 544
A project stakeholder approaches the project manager and wishes to know how long the vendor will provide support for the application being developed for the project.
This information should be provided during the:
A. closure meeting.
B. kickoff meeting.
C. stand-up meeting.
D. team meeting.
Correct Answer:
C. stand-up meeting.
Exam Question 545
A project team lacks the necessary team members to complete a project. The project manager has rejected numerous candidates.
This is an example of:
A. outsourcing.
B. low-quality resources.
C. benched candidates.
D. resource planning.
Correct Answer:
D. resource planning.
Exam Question 546
A project manager at a projectized organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits and jeopardizes the commitment date.
Which of the following should the project manager do NEXT?
A. Ask the functional manager to release the 20% of allocation from the secondary project.
B. Ask the sponsor to negotiate with the project manager from the secondary project.
C. Ask the PMO to assign additional resources.
D. Ask the project manager of the secondary project to release the resource.
Correct Answer:
A. Ask the functional manager to release the 20% of allocation from the secondary project.
Exam Question 547
Which of the following project phases occurs when requirements are detailed?
A. Initiation
B. Monitor and control
C. Planning
D. Closing
Correct Answer:
C. Planning
Exam Question 548
Based on the table below:
Which of the following is the float of Task B?
A. -2
B. 0
C. 2
D. 5
Correct Answer:
B. 0
Exam Question 549
Which of the following BEST describes the relationship between portfolios, projects, and programs?
A. A group of programs makes up a project, and all of an organization’s projects make up a portfolio.
B. A group of projects makes up a program, and all of an organization’s programs make up a portfolio.
C. A group of portfolios makes up a program, and all of an organization’s programs make up a project.
D. A group of projects makes up a portfolio, and all of an organization’s portfolios make up a program.
Correct Answer:
B. A group of projects makes up a program, and all of an organization’s programs make up a portfolio.
Exam Question 550
A customer has requested a new feature be included in the next iterative release. The customer has agreed to move a previously planned feature to a subsequent release and increase the budget. Which of the following is the MOST appropriate scheduling action?
A. Analyze the critical path and update the WBS with the new feature
B. Add the new feature and reprioritize the product backlog
C. Add the new feature to the next sprint and move the old feature to the following sprint
D. Conduct a retrospective with the team to discuss the change and introduce the feature
Correct Answer:
C. Add the new feature to the next sprint and move the old feature to the following sprint