Exam Question 511

Which of the following captures unforeseen activities throughout the project that need attention and resolution?

A. Gantt chart
B. Action items
C. Project schedule
D. Meeting minutes
Correct Answer:
A. Gantt chart

Exam Question 512

A project manager is required to maintain various documents and procedures.
Which of the following require ongoing attention and periodic updates?

A. Project charter
B. Change requests
C. Project management plan
D. Communication plan
E. Project SOW
Correct Answer:
C. Project management plan

Exam Question 513

Based on the table below:

Which of the following is the critical path if Task B has extended to ten days?
Which of the following is the critical path if Task B has extended to ten days?

A. 21 days
B. 23 days
C. 24 days
D. 26 days
Correct Answer:
D. 26 days

Exam Question 514

Given the information in the table below, which of the following is the total project cost?

Which of the following is the total project cost?

A. $40,000
B. $70,000
C. $95,000
D. $120,000
Correct Answer:
B. $70,000

Exam Question 515

A project team is identifying, rating the probability of, and determining the impact on potential problems throughout the project. The team is also including the corresponding actions to take.
Which of the following activities does this describe?

A. Risk identification
B. Risk quantification
C. Risk planning
D. Risk qualification
Correct Answer:
C. Risk planning

Exam Question 516

A new corporate policy was approved that will positively affect the project.
Which of the following should the project manager do FIRST?

A. Schedule the change
B. Review the communication plan
C. Update the issue log
D. Update the risk register
Correct Answer:
B. Review the communication plan

Exam Question 517

On an OBS chart, there is a dashed line between some team members and the project manager, and there is a solid line connecting other members to the project manager. Additionally, some employees at a lower level on the chart have no connection to the project manager.
Which of the following does this signify?

A. Horizontally aligned organization
B. Vertically aligned organization
C. Matrix aligned organization
D. Project aligned organization
Correct Answer:
C. Matrix aligned organization

Exam Question 518

A fire occurred in the production facility over the weekend, affecting the machinery being used to produce a deliverable. No injuries were reported.
Which of the following is MOST appropriate for the project manager to do NEXT?

A. Refer to the contingency plan
B. Conduct an immediate emergency team meeting
C. Perform a SWOT analysis
D. Implement the risk response plan
Correct Answer:
A. Refer to the contingency plan

Exam Question 519

Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Choose two.)

A. Planned value
B. Schedule variance
C. Acceptable variance
D. Cost variance
E. Earned value
Correct Answer:
D. Cost variance
E. Earned value

Exam Question 520

A project manager needs status on the project timeline.
Which of the following team members should provide an update?

A. Product owner
B. Business analyst
C. Scheduler
D. Sponsor
Correct Answer:
C. Scheduler