The latest CompTIA Project+ PK0-004 certification actual real practice exam question and answer (Q&A) dumps are available free, which are helpful for you to pass the CompTIA Project+ PK0-004 exam and earn CompTIA Project+ PK0-004 certification.

CompTIA Project+ PK0-004 Exam Questions and Answers

Exam Question 381

The quarterly financial statement has been released, and portfolios are losing funding for projects.
Which of the following options are MOST appropriate to keep the project alive and on schedule? (Choose two.)

A. Shorten the project duration.
B. Reduce the features being released.
C. Request more time with a smaller project team.
D. Reduce quality control.
E. Ask for operational team support.
Correct Answer:
B. Reduce the features being released.
D. Reduce quality control.

Exam Question 382

The government wants to start a project that will launch a satellite but lacks the appropriate SMEs.
Which of the following would be BEST to solicit vendors?

A. LOI
B. RFQ
C. RFI
D. SOW
Correct Answer:
C. RFI

Exam Question 383

A project manager has gathered time estimates for a new project’s activities and is now ready to begin developing the schedule.
Which of the following would the project manager most likely do NEXT?

A. Create a WBS.
B. Determine predecessors and dependencies.
C. Determine the critical path.
D. Prioritize tasks.
Correct Answer:
A. Create a WBS.

Exam Question 384

A project team member has completed an assigned task on time.
After updating the project schedule, which of the following steps should the project manager take NEXT?

A. Send an updated schedule to the CCB.
B. Send a project status update to the sponsor.
C. Release the team members to the functional manager.
D. Notify the team members to begin successor tasks.
Correct Answer:
C. Release the team members to the functional manager.

Exam Question 385

After SOW and contract approvals, the project manager plans to schedule a meeting with the business analyst and several end users.
The project manager’s main objective in this meeting is to:

A. identify resources
B. baseline the schedule
C. create deliverables
D. define requirements
Correct Answer:
D. define requirements

Exam Question 386

A project’s stakeholders have not been informed of project updates and milestones by the CCB and project team. The stakeholders have threatened to withdraw project support.
Which of the following should the project manager do to get buy-in from the stakeholders for the project?

A. Update the communications plan to include the stakeholders
B. Expedite completion of the project before support is withdrawn by the stakeholders
C. Revise the quality management plan to include the project stakeholders
D. Increase the number of status reports provided to the project stakeholders
Correct Answer:
A. Update the communications plan to include the stakeholders

Exam Question 387

Two parties are beginning conversations regarding the purchase of professional services.
Which of the following should be in place FIRST?

A. RFP
B. SOW
C. NDA
D. LOI
Correct Answer:
A. RFP

Exam Question 388

A vendor is late with product deliverables.
Which of the following documents should the PM refer to FIRST?

A. C&D letter
B. MOU
C. SLA
D. SOW
Correct Answer:
C. SLA

Exam Question 389

A developer is experiencing constant project scope changes and reaches out to the project manager to discuss the situation. They agree the customer has requested multiple modifications to the core idea and now extra work may need to be performed.
Which of the following approaches would BEST support on-time delivery considering these changes?

A. Strict change management controls
B. Regular Scrum meetings
C. Continuous requirements gathering
D. Regular milestone reviews
Correct Answer:
A. Strict change management controls

Exam Question 390

At each project team meeting, the project team raises the same risk repeatedly. A mitigation plan has been developed since the risk was initially identified.
Which of the following risk activities is MOST likely missing since the identification?

A. Quantification
B. Response
C. Prioritization
D. Communication
E. Review
Correct Answer:
E. Review