Exam Question 371
The stakeholders who are available for the user acceptance test do not understand the project’s requirements. The tester is trying to identify who requested the feature, but there is no information available.
Which of the following components is missing?
A. RTM
B. Quality plan
C. Project schedule
D. SOW
Correct Answer:
B. Quality plan
Exam Question 372
Which of the following are the components of a RACI matrix?
A. Responsibility, authority, support, inform
B. Responsible, accountable, consulted, informed
C. Reliability, accountability, support, inform
D. Responsibility, acquired, consulted, informed
Correct Answer:
A. Responsibility, authority, support, inform
B. Responsible, accountable, consulted, informed
Exam Question 373
A project team is creating a new product, and stakeholders are having a hard time understanding the product.
Which of the following should be sent to the stakeholders?
A. Printed sketches and potential uses
B. Memo outlining high-level requirements
C. Sponsor mandate for the product
D. Link to the project’s intranet site to review status reports
Correct Answer:
A. Printed sketches and potential uses
Exam Question 374
While planning a project, the project team estimates known expenses but also applies a margin of error for unknown expenses.
Which of the following is the project team trying to determine?
A. Cost of quality
B. Expenditures
C. Total project cost
D. Burn rate
Correct Answer:
C. Total project cost
Exam Question 375
Language barriers will MOST likely influence a PM to:
A. use more print media to communicate with the stakeholders.
B. hire a bilingual project team that is fluent in the language to reduce conflict.
C. hire an interpreter to ensure verbal and written communications are accurate.
D. learn the unknown language to be able to communicate effectively with stakeholders.
Correct Answer:
B. hire a bilingual project team that is fluent in the language to reduce conflict.
Exam Question 376
A customer has requested a change in an active project.
Which of the following actions should the project manager take FIRST?
A. Gather input from the team.
B. Inform the end user of the change.
C. Submit the change request to the project sponsor.
D. Update the change log.
Correct Answer:
C. Submit the change request to the project sponsor.
Exam Question 377
A project manager has received documented approval from management to begin a project and the authority to start assigning resources to the project.
The project manager has received the:
A. project charter.
B. statement of work.
C. project plan.
D. project request.
Correct Answer:
A. project charter.
Exam Question 378
A project manager wishes to track a project’s performance against the original approved schedule.
Which of the following steps is necessary to capture the needed information?
A. Determine the critical path.
B. Determine the milestones.
C. Set phase gates
D. Set a baseline.
Correct Answer:
D. Set a baseline.
Exam Question 379
Team members in a projectized organization are released at the end of a project and placed on the “bench”.
Which of the following should the benched team members do NEXT?
A. Find a new project.
B. Check in with a functional manager.
C. Report to the project manager.
D. Contact the project sponsor.
Correct Answer:
B. Check in with a functional manager.
Exam Question 380
Which of the following is the BEST method to provide quick status updates on project tasks without interrupting project activities?
A. Phone call
B. Interoffice mail
C. Newsletter
D. Internal collaboration site
Correct Answer:
B. Interoffice mail