Exam Question 351

A project sponsor approaches the project manager with a change request. During the conversation, the project sponsor claims to understand the impact of the change to the project length and has the budget to handle the cost. The sponsor also tells the project manager to send whatever needs a signature.
The project manager’s NEXT step should be to:

A. document the change
B. implement the change
C. communicate the change
D. prioritize the change
Correct Answer:
A. document the change

Exam Question 352

A functional manager within a project is requesting to edit the display features of an application that is being developed.
Which of the following has the authority to approve the edit?

A. PM
B. CCB
C. PMO
D. SME
Correct Answer:
A. PM

Exam Question 353

Which of the following documents is a snapshot in time of a project during the execution phase?

A. Scope document
B. Performance indicators
C. Status report
D. Risk register
Correct Answer:
C. Status report

Exam Question 354

Which of the following project roles is ultimately responsible for all project artifacts?

A. Project sponsor
B. Project coordinator
C. Project manager
D. Project team
Correct Answer:
C. Project manager

Exam Question 355

Which of the following is a component of the project cost control?

A. Scope statement
B. Burn rate
C. MOU
D. SLA
Correct Answer:
A. Scope statement

Exam Question 356

An engineer is troubleshooting a malfunctioning physical deliverable and requires assistance from remote team members.
Which of the following would be the BEST communication method for the engineer to use?

A. Phone conversation
B. Face-to-face meeting
C. Instant messaging
D. Video conference
Correct Answer:
D. Video conference

Exam Question 357

Which of the following project management roles is responsible for estimating the duration of tasks?

A. Project scheduler
B. Project team
C. Project manager
D. Project coordinator
Correct Answer:
C. Project manager

Exam Question 358

A project manager wishes to track a project’s performance against the original approved schedule.
Which of the following steps is necessary to capture the needed information?

A. Determine the critical path.
B. Determine the milestones.
C. Set phase gates
D. Set a baseline.
Correct Answer:
D. Set a baseline.

Exam Question 359

A stakeholder with whom the project manager has worked on numerous occasions drops by and requests that the project management add two small items to the application under development. The stakeholder has seen the value of these changes in other applications and assures the project manager they are easy, quick changes.
Which of the following BEST describes how the project manager should respond?

A. Take the request to the CCB
B. Quickly make the changes
C. Ask a project team member to make the changes
D. Inform the sponsor of the stakeholder’s request
Correct Answer:
C. Ask a project team member to make the changes

Exam Question 360

An approved change was implemented.
Which of the following should be accomplished NEXT?

A. Update the documentation.
B. Validate the change.
C. Update the project sponsor.
D. Validate the impact.
Correct Answer:
A. Update the documentation.