Skip to Content

CompTIA Project+ PK0-004 Exam Questions and Answers – 4

The latest CompTIA Project+ PK0-004 certification actual real practice exam question and answer (Q&A) dumps are available free, which are helpful for you to pass the CompTIA Project+ PK0-004 exam and earn CompTIA Project+ PK0-004 certification.

CompTIA Project+ PK0-004 Exam Questions and Answers

Exam Question 341

Which of the following methods should a project manager use to improve email communication for a time- sensitive, high-visibility global project? (Choose two.)

A. Limit email recipients to only required team members.
B. Increase the number of emails to encourage team interaction.
C. Set up emails with bold text and all caps in the subject line.
D. Eliminate acronyms from the email to avoid miscommunication.
E. Include more information to increase the length of each email message.
F. Include detailed technical consideration in each email.
Correct Answer:
A. Limit email recipients to only required team members.
B. Increase the number of emails to encourage team interaction.

Exam Question 342

A project sponsor asks if a construction project can be accelerated to meet a new timeline. The project manager analyzes the schedule and finds insufficient float to accommodate the new delivery date.
If more resources are provided, which of the following strategies would BEST help to achieve the new date?

A. Fast track
B. Burn
C. Crash
D. Reduce durations
Correct Answer:
A. Fast track

Exam Question 343

A Scrum team is completing a sprint; however, some tasks will need to carry over to the next sprint.
Which of the following should the Scrum master do to improve the team’s velocity in the next sprint?

A. Take a more hands-on leadership approach.
B. Add the unfinished work to the backlog.
C. Schedule a sprint retrospective.
D. Hold additional daily stand-up meetings.
Correct Answer:
B. Add the unfinished work to the backlog.

Exam Question 344

A concrete pad needs to be laid for a new house and requires three days to cure. The project manager notes that rain may be in the immediate forecast.
Which of the following would BEST avoid the risk of rain damage?

A. Place a tarp over the fresh concrete to protect it.
B. Refinish the concrete if it rains during that time.
C. Pour the concrete as quickly as possible to allow the most drying time.
D. Wait to pour the concrete until rain is not in the forecast.
Correct Answer:
C. Pour the concrete as quickly as possible to allow the most drying time.

Exam Question 345

A project manager has updated the project schedule but cannot analyze the schedule performance.
Which of the following steps did the project manager miss?

A. Lock the schedule
B. Approve the schedule
C. Baseline the schedule
D. Fast track the schedule
Correct Answer:
C. Baseline the schedule

Exam Question 346

A project manager is collecting work package information from the project team for the first time.
Which of the following elements should the project manager have at the end of the meeting?

A. Task name, duration, and dependencies
B. Task leveling, baseline, and critical path
C. Task assignments, quality requirements, and project governance sign-off
D. Task start, finish, and estimate cost
Correct Answer:
C. Task assignments, quality requirements, and project governance sign-off

Exam Question 347

A project sponsor promises the Chief Executive Officer (CEO) that a project will be completed before the next quarterly meeting.
The project manager needs to take the following elements into account:

  • Delivery
  • Vacation
  • Cost of overtime
  • Work effort

Which of the following documents should the project manager use to guarantee the project’s success?

A. RACI
B. Schedule
C. Project charter
D. SWOT
E. Burn chart
Correct Answer:
E. Burn chart

Exam Question 348

As part of the early stages of a potential corporate acquisition, which of the following documents should the acquiring organization complete, showing regulators and investors the offered purchase price and target closing date?

A. Sales contract
B. Memorandum of agreement
C. Letter of intent
D. Purchase order
Correct Answer:
A. Sales contract

Exam Question 349

A project manager was reprimanded for failing to complete timely status reports and providing mixed messaging about a project’s performance.
Which of the following would be responsible for discussing and resolving this issue?

A. Project coordinator
B. Project stakeholder
C. Project management office
D. Project sponsor
Correct Answer:
C. Project management office

Exam Question 350

A project manager is overseeing the construction of a new building. There are likely existing underground water, gas, and electrical lines.
Which of the following is an example of mitigation?

A. Trust the contractor to do the job well because the company has been in business for a long time.
B. Tell the contractor that the company is responsible for any damage done to underground lines.
C. Immediately fix any broken lines that are hit during construction.
D. Ensure the contractor has the appropriate utility maps.
Correct Answer:
D. Ensure the contractor has the appropriate utility maps.