Exam Question 331

A project facilitator is working within a large project team that includes 36 members representing different organizational groups. The current communications plan calls for full status updates to be emailed to the whole group twice per week.
Which of the following factors should be considered FIRST when communicating with this group?

A. Providing all parties with frequent updates keeps the team on the same page as the project moves forward.
B. The large team may be dispersed over different time zones, preventing the team from receiving the status updates at the same time.
C. The frequency, method, and level of detail provided should be different for each target audience.
D. All team members receive the same level of detail, ensuring the accuracy of the status updates
Correct Answer:
D. All team members receive the same level of detail, ensuring the accuracy of the status updates

Exam Question 332

A sports event is coming to a local city, and the project manager for the event fears there might be violence if the local team wins.
Which of the following types of project activities would occur if the local team wins?

A. Applying a risk mitigation plan
B. Securing appropriate funding
C. Implementing quality control measures
D. Changing the timeline
Correct Answer:
A. Applying a risk mitigation plan

Exam Question 333

The project team has identified all the tasks needed to create project deliverables and grouped them into work packages covering all project scope.
Which of the following should be done NEXT?

A. Identify task relationships.
B. Put the resources on tasks.
C. Set the quality gates.
D. Estimate the work package.
Correct Answer:
D. Estimate the work package.

Exam Question 334

A project manager is developing a risk management plan and has decided to score each risk based on composite score of impact and probability. In discussions with the project sponsor, they determined that all risks with a composite score lower than 1 will not receive further attention.

In discussions with the project sponsor, they determined that all risks with a composite score lower than 1 will not receive further attention.

Which of the following risks should the project manager accept? (Choose two.)

A. 1
B. 2
C. 3
D. 4
E. 5
F. 6
Correct Answer:
C. 3
E. 5

Exam Question 335

Project A is delivering the foundation for Project B. Construction regulations have changed during Project A, requiring work to be redone in the allocated buffer.
Which of the following is the MOST likely impact to Project B?

A. The cost will increase.
B. There will be no impact.
C. The scope will change.
D. The schedule will change.
Correct Answer:
D. The schedule will change.

Exam Question 336

A project has just begun, and people are not clear about the objectives.
Which of the following meeting types is needed?

A. Stand-up
B. Scheduling
C. Impromptu
D. Kickoff
Correct Answer:
A. Stand-up

Exam Question 337

An external customer has requested a modification of the project scope through an official change request.
Which of the following is the appropriate NEXT step?

A. Implement the change.
B. Analyze impacts to the project.
C. Create a new change request.
D. Modify the configuration documentation.
Correct Answer:
B. Analyze impacts to the project.

Exam Question 338

A manager is reviewing some projects with two project managers who are working on the financial system.
Which of the following BEST describes this type of review?

A. Operations
B. Project
C. Portfolio
D. Program
Correct Answer:
C. Portfolio

Exam Question 339

A firm, fixed-price project is on pace to exceed the maximum defect rate identified in the project charter. The customer has stated the project must be delivered on time.
Which of the following is the BEST option for the project to complete on time and within parameters?

A. Reduce the project scope.
B. Crash the schedule.
C. Request additional budget from the customer.
D. Apply new resources to the project.
Correct Answer:
B. Crash the schedule.

Exam Question 340

A fire alarm goes off in the building where the project team works. Employees are instructed to leave the premises immediately using the stairs; they are not to use elevators, and they must gather in one place outside the building for further instructions.
This is known as a:

A. business change response
B. change management response
C. business continuity response
D. risk management response
Correct Answer:
D. risk management response