CompTIA Project+ PK0-004 Exam Questions and Answers – 4

The latest CompTIA Project+ PK0-004 certification actual real practice exam question and answer (Q&A) dumps are available free, which are helpful for you to pass the CompTIA Project+ PK0-004 exam and earn CompTIA Project+ PK0-004 certification.

CompTIA Project+ PK0-004 Exam Questions and Answers

Exam Question 311

A company was originally organized using a functional structure; however, the company has decided to go forward with a matrix structure to get the most utilization of resources.
This is an example of:

A. a business process change
B. personal preference
C. internal reorganization
D. intraorganizational differences
Correct Answer:
C. internal reorganization

Exam Question 312

Using Scrum, which of the following are discussed in a daily standup meeting?

A. What was done yesterday, what is planned for today, and what roadblocks need to be removed
B. What was done yesterday, what is planned for the week, and what issues were resolved
C. What was done yesterday, what is planned for today, and what deliverables were completed
D. What was done yesterday, what is planned for this week, and what items from the backlog are priority
Correct Answer:
A. What was done yesterday, what is planned for today, and what roadblocks need to be removed

Exam Question 313

Which of the following project phases would MOST likely include a creating transition plan?

A. Closing
B. Initiation
C. Execution
D. Planning
Correct Answer:
D. Planning

Exam Question 314

While preparing to plan a project, the project manager meets with the key stakeholders to determine the flexibility between the project constraints .
Which of the following techniques should the project manager consider to reduce personal bias and increase buy-in?

A. Send the stakeholders a survey about the project constraints to complete anonymously
B. Watch and determine which constraint is most important
C. Compare the constraints two at a time and have the stakeholders vote on importance
D. Look at historical information regarding the flexibility preferences of key stakeholders
Correct Answer:
A. Send the stakeholders a survey about the project constraints to complete anonymously

Exam Question 315

A team member has reported Task 3 will be completed ahead of schedule.

A team member has reported Task 3 will be completed ahead of schedule.

Using the given chart, which of the following represents the critical path if Task 3 is completed in two days?

A. 8 days
B. 10 days
C. 11 days
D. 12 days
Correct Answer:
D. 12 days

Exam Question 316

In the review of a project status report, the slack is negative.
Which of the following should the project manager tell the stakeholders?

A. The project is behind schedule
B. The project is over budget
C. The project has float available
D. The project needs a gate review
Correct Answer:
A. The project is behind schedule

Exam Question 317

Many questions have arisen regarding a newly identified project. Project team members are anxious to know who will be part of the team and what the project will deliver.
Which of the following would be the BEST way to provide this information?

A. Kickoff meeting
B. Status report
C. Company-wide email
D. CCB meeting
Correct Answer:
A. Kickoff meeting

Exam Question 318

A project sponsor wants to know when the plan changed to ship the deliverables to a new location.
To determine the answer, the project manager should FIRST review the:

A. project management plan
B. scope statements and issue log
C. project dashboard and status report
D. action items and meeting minutes
Correct Answer:
B. scope statements and issue log

Exam Question 319

Which of the following documents are considered mutually binding? (Choose two.)

A. NDA
B. PO
C. RFP
D. WBS
E. KPI

Correct Answer:
A. NDA
C. RFP

Exam Question 320

The diagram or chart should include cause effect analysis and investigate historical information.
Which of the following should be used given these requirements?

A. Pareto Chart
B. Ishikawa Diagram
C. Histogram
D. Probability diagram
E. Run chart
F. Scatter chart
Correct Answer:
F. Scatter chart