Exam Question 391

During planning, a project coordinator publishes the project management plan. After reviewing the plan, the project sponsor is concerned it is too long and detailed.
Which of the following does the project sponsor desire?

A. Status report
B. Task durations
C. Project schedule
D. Schedule management plan
Correct Answer:
A. Status report

Exam Question 392

In which of the following circumstances would faxing be the MOST appropriate communication method?

A. When sending confidential information
B. When resolving complex issues
C. When providing weekly status updates
D. When signatures are required
Correct Answer:
D. When signatures are required

Exam Question 393

A team member has finalized a discussion with the board of directors, but the Chief Financial Officer (CFO) is complaining about the large amount of money the project requires.
Which of the following is the BEST change control process to follow?

A. Identify, implement, approve, evaluate, validate, update, communicate
B. Identify, evaluate, approve, implement, validate, update, communicate
C. Identify, approve, evaluate, implement, validate, update, communicate
D. Identify, validate, evaluate, approve, implement, update, communicate
Correct Answer:
B. Identify, evaluate, approve, implement, validate, update, communicate

Exam Question 394

The PMO has removed a vendor from a project for inflating costs and failing to complete deliverables in a timely manner. The PMO received complaints that vendor resources missed appointments and provided poor service. The vendor has initiated a lawsuit against the PMO, asserting the vendor was operating within the terms of the current agreement.
Which of the following documents should be reviewed by the PMO to support vendor removal? (Choose two.)

A. Communication plan
B. Project charter
C. Service level agreement
D. Project management plan
E. Action items
F. Statement of work
Correct Answer:
C. Service level agreement
F. Statement of work

Exam Question 395

A hurricane occurs in an area where several key project resources are located. When reviewing the project dashboard, the project sponsor sees the project is behind schedule and asks the project manager for an explanation.
Which of the following documents should the project manager examine NEXT to provide an explanation?

A. Meeting minutes
B. Issue log
C. Project schedule
D. Budget
Correct Answer:
B. Issue log

Exam Question 396

A project manager creates a Pareto chart based on the table below:

A project manager creates a Pareto chart based on the table.

Which of the following describes why the team was asked to inspect and review missing parts, poor adhesives, and faulty installation?

A. To take preventive action and identify the causes resulting in the highest number of issues
B. To take corrective action and identify the effects resulting in the highest number of issues
C. To take preventive action and identify and frequencies resulting in the highest number of issues
D. To take corrective action and identify the causes resulting in the highest number of issues
Correct Answer:
A. To take preventive action and identify the causes resulting in the highest number of issues

Exam Question 397

A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized.

A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized.

Which of the following is the NEXT appropriate step for the project manager to take?

A. Identify risk strategies for the realized events
B. Change the risk status to closed for 2 and 6
C. Consult the risk management plan
D. Update the issue log
Correct Answer:
A. Identify risk strategies for the realized events

Exam Question 398

A company just announced all third-party vendors must provide ten cybersecurity resources within six weeks.
Which of the following documents should the project manager create LAST?

A. RFI
B. NDA
C. MOU
D. RFQ
Correct Answer:
C. MOU

Exam Question 399

A PM has a complex project that requires coordination among numerous stakeholders.
Which of the following is the MOST appropriate type of meeting for the stakeholders to hold?

A. Virtual
B. Impromptu
C. One-on-one
D. In-person
Correct Answer:
A. Virtual

Exam Question 400

A project is approaching its end when the project manager is informed that a deliverable is exceeding the upper noise limit set by the legislation of the country where it was implemented.
Which of the following constraints has MOST likely been overlooked?

A. Scope
B. Resources
C. Environment
D. Quality
Correct Answer:
C. Environment