Question
You are implementing master planning and need to establish coverage time fences to avoid premature supply suggestions.
You need to understand how coverage time fences affect input data for master planning.
What should you do?
A. The resulting planned orders will be delayed by the number of days specified in the coverage time fence.
B. The resulting planned orders will be moved to the next available date within the coverage time fence.
C. The resulting planned orders might have a date that is after today’s date plus the coverage time fence.
D. The resulting planned orders will be cancelled.
Answer
C. The resulting planned orders might have a date that is after today’s date plus the coverage time fence.
Explanation
If delays occur, the resulting planned orders might have a date that is after today’s date plus the coverage time fence. The other options describe actions that do not occur when delays happen in relation to coverage time fences.
Microsoft Dynamics 365 Supply Chain Management Functional Consultant MB-330 certification exam assessment practice question and answer (Q&A) dump including multiple choice questions (MCQ) and objective type questions, with detail explanation and reference available free, helpful to pass the Microsoft Dynamics 365 Supply Chain Management Functional Consultant MB-330 exam and earn Microsoft Dynamics 365 Supply Chain Management Functional Consultant MB-330 certification.