Skip to Content

Lean Six Sigma Green Belt: How Does the Critical Path Method Determine Project’s Minimum Duration?

What Is the Difference Between Critical Path Tasks and Tasks with Float?

Master the Critical Path Method (CPM) for your project management and Six Sigma certification. Learn how identifying the longest sequence of dependent tasks determines the total project duration and why tasks on this path have zero float, meaning any delay impacts your deadline.

Question

What does the critical path in project management identify?

A. The longest sequence of dependent tasks determining project duration
B. The cheapest sequence of project tasks
C. The tasks requiring the least resources
D. Tasks that can be delayed without affecting deadlines

Answer

A. The longest sequence of dependent tasks determining project duration

Explanation

Critical path drives the minimum project completion time. The critical path in project management identifies the longest sequence of dependent tasks, and the total duration of this sequence determines the shortest possible completion time for the entire project.​

The Critical Path Method (CPM)

The Critical Path Method is a project management technique used to plan and schedule the tasks in a project. It provides a visual representation of the project’s tasks and shows the dependencies between them. By identifying the longest path of dependent activities, project managers can determine the minimum time required to complete the project. Any delay in a task on the critical path will directly delay the project’s completion date.​

Key Concepts:

  • Task Dependencies: In any project, some tasks cannot begin until others are completed. The critical path maps the longest chain of these interconnected tasks.​
  • Longest Path, Shortest Duration: While it may seem counterintuitive, the longest path of dependent tasks dictates the shortest possible project duration. This is because all tasks on this path must be completed in sequence, and the project cannot finish until the last task on this path is done.
  • Zero Float: Tasks that lie on the critical path have zero “float” or “slack.”​

Float or Slack

The concept of float is crucial for understanding why the other options are incorrect. Float (or slack) is the amount of time a task can be delayed without affecting subsequent tasks or the project’s overall completion date.​

  • Critical Path Tasks: Have zero float. Their start and end dates are fixed, and any delay will push back the project deadline.
  • Non-Critical Tasks: Have positive float. These tasks can be delayed for a certain period without impacting the project’s completion. This flexibility allows project managers to reallocate resources from non-critical tasks to critical ones if needed.​

Explanation of Incorrect Options

B. The cheapest sequence of project tasks: The critical path is determined by task duration and dependencies, not by cost. While cost is a critical project constraint, it is not what the critical path identifies.

C. The tasks requiring the least resources: Similar to cost, resource allocation is a separate planning consideration. The critical path focuses solely on the time required to complete tasks.

D. Tasks that can be delayed without affecting deadlines: These are, by definition, tasks that are not on the critical path. They have float, which allows for scheduling flexibility.​

Lean Six Sigma Green Belt: Apply & Master Skills certification exam assessment practice question and answer (Q&A) dump including multiple choice questions (MCQ) and objective type questions, with detail explanation and reference available free, helpful to pass the Lean Six Sigma Green Belt: Apply & Master Skills exam and earn Lean Six Sigma Green Belt: Apply & Master Skills certificate.