Scrum PSM I: Which are appropriate topics for discussion in Sprint Retrospective?

Question

Which are appropriate topics for discussion in a Sprint Retrospective? (Choose three.)

A. Arranging the Sprint Backlog for the next Sprint.
B. The value of work currently represented in the Product Backlog.
C. Team relations
D. Definition of Done.
E. How the Scrum Team does its work.

Answer

B. The value of work currently represented in the Product Backlog.
C. Team relations
E. How the Scrum Team does its work.

Explanation

Based on this definition, I think the appropriate topics for discussion in a Sprint Retrospective are:

C. Team relations: This topic relates to how the Scrum Team members interacted and collaborated with each other and with other stakeholders during the Sprint. It may include feedback, appreciation, recognition, conflicts, communication, trust, alignment, etc. Discussing team relations can help improve team morale, cohesion, performance and satisfaction.

D. Definition of Done: This topic relates to the shared understanding of what it means for a Product Backlog item or an Increment to be complete and potentially releasable. It may include quality standards, acceptance criteria, testing methods, documentation requirements, etc. Discussing the Definition of Done can help ensure transparency, consistency and quality of the work done by the Scrum Team.

E. How the Scrum Team does its work: This topic relates to the process and tools that the Scrum Team used to plan, execute and deliver its work during the Sprint. It may include Sprint Planning, Daily Scrum, Sprint Review, backlog management, estimation techniques, engineering practices, collaboration tools, etc. Discussing how the Scrum Team does its work can help identify best practices, inefficiencies, impediments and opportunities for improvement.

Therefore, I think the best answers to your question are:

C. Team relations
D. Definition of Done.
E. How the Scrum Team does its work.

These are appropriate topics for discussion in a Sprint Retrospective because they can help the Scrum Team inspect and adapt its way of working and increase its quality and effectiveness for the next Sprint. The other options are not appropriate topics for discussion in a Sprint Retrospective because they are not related to how the last Sprint went or how to improve for the next Sprint. For example:

A. Arranging the Sprint Backlog for the next Sprint: This topic relates to selecting and ordering Product Backlog items that will be delivered in the next Sprint. This is not a topic for discussion in a Sprint Retrospective because it is part of Sprint Planning, which is a separate event that takes place after the Sprint Retrospective.

B. The value of work currently represented in the Product Backlog: This topic relates to estimating and prioritizing Product Backlog items based on their expected value for customers and stakeholders. This is not a topic for discussion in a Sprint Retrospective because it is part of Product Backlog refinement, which is an ongoing activity that can happen throughout the Sprint.

Reference

Scrum Professional Scrum Master PSM I certification exam practice question and answer (Q&A) dump with detail explanation and reference available free, helpful to pass the Scrum Professional Scrum Master PSM I exam and earn Scrum Professional Scrum Master PSM I certification.