Skip to Content

PRINCE2 Practitioner: Appointing the Project Manager

Discover who is responsible for appointing the Project Manager in PRINCE2 methodology. Learn the roles and responsibilities of key stakeholders in PRINCE2 projects.

Table of Contents

Question

Who is responsible for appointing the Project Manager?

A. Corporate or Programme Management
B. The Project Board
C. The Executive
D. Project Assurance

Answer

A. Corporate or Programme Management

Explanation

In PRINCE2, Corporate or Programme Management is responsible for appointing the Project Manager. They ensure the project aligns with the organization’s strategic objectives and provide the necessary resources and support.

The Project Board, Executive, and Project Assurance play important roles but do not appoint the Project Manager:

  • The Project Board is the project’s key decision-making body, providing overall direction and control.
  • The Executive is the senior user on the Project Board, ensuring the project delivers the desired outcome and benefits.
  • Project Assurance independently monitors project progress and performance on behalf of the Project Board.

PRINCE2 Practitioner certification exam practice question and answer (Q&A) dump with detail explanation and reference available free, helpful to pass the PRINCE2 Practitioner exam and earn PRINCE2 Practitioner certification.