Discover who is responsible for appointing the Project Manager in PRINCE2 methodology. Learn the roles and responsibilities of key stakeholders in PRINCE2 projects.
Table of Contents
Question
Who is responsible for appointing the Project Manager?
A. Corporate or Programme Management
B. The Project Board
C. The Executive
D. Project Assurance
Answer
A. Corporate or Programme Management
Explanation
In PRINCE2, Corporate or Programme Management is responsible for appointing the Project Manager. They ensure the project aligns with the organization’s strategic objectives and provide the necessary resources and support.
The Project Board, Executive, and Project Assurance play important roles but do not appoint the Project Manager:
- The Project Board is the project’s key decision-making body, providing overall direction and control.
- The Executive is the senior user on the Project Board, ensuring the project delivers the desired outcome and benefits.
- Project Assurance independently monitors project progress and performance on behalf of the Project Board.