PRINCE2 Foundation: Time-Driven Controls for Monitoring Progress

Learn about time-driven controls in PRINCE2 Foundation and how they are used to monitor the progress of work packages and management stages at predefined intervals.

Table of Contents

Question

Which statement about time-driven controls is CORRECT?

A. Time-driven controls are used for monitoring the progress of work packages and management stages
B. Time-driven controls take place when specific events happen
C. Time-driven controls are produced at the end of a stage
D. An exception report is a time-driven control

Answer

A. Time-driven controls are used for monitoring the progress of work packages and management stages

Explanation

A. Time-driven controls are used for monitoring the progress of work packages and management stages. Time-driven controls are periodic reviews or reports based on predefined intervals or frequencies, such as daily, weekly, or monthly. They help track progress, assess performance, and identify potential issues or deviations from plans for both work packages and management stages.

PRINCE2 Foundation certification exam practice question and answer (Q&A) dump with detail explanation and reference available free, helpful to pass the PRINCE2 Foundation exam and earn PRINCE2 Foundation certification.