Learn how to deal with deliverables that do not meet performance requirements in software projects, and test your knowledge with a PMP exam question.
Table of Contents
Question
In a software development project, some of the deliverables do not meet specific performance requirements.
What action should the project manager take?
A. Review the issues with the project team to address the issues.
B. Review the requirements traceability matrix at the next meeting.
C. Report issues to key stakeholders and discuss follow up actions.
D. Ensure compliance with the quality management plan.
Answer
C. Report issues to key stakeholders and discuss follow up actions.
Explanation
The project manager should communicate the issues to the key stakeholders as soon as possible and seek their input on how to resolve them. This will help to maintain trust and transparency, as well as to align the expectations and priorities of the stakeholders. Reviewing the issues with the project team, the requirements traceability matrix, or the quality management plan are all important steps, but they should be done after informing the stakeholders.
Reference
Project Management Professional PMI-PMP certification exam practice question and answer (Q&A) dump with detail explanation and reference available free, helpful to pass the Project Management Professional PMI-PMP exam and earn Project Management Professional PMI-PMP certification.