Question
A Scrumban team member wants to know what work has been completed this week. Which chart should the team member review?
A. Gantt chart
B. Feature chart
C. Kanban chart
D. Burndown chart
Answer
C. Kanban chart
Explanation
In a Scrumban environment, which combines elements of Scrum and Kanban methodologies, the Kanban chart is the most appropriate tool for a team member to review completed work on a weekly basis. Here’s why:
- Kanban Chart: This visual management tool is central to both Kanban and Scrumban methodologies. It provides a real-time representation of work items as they move through different stages of the workflow. The chart typically includes columns such as “To Do,” “In Progress,” and “Done.” By reviewing the Kanban chart, a team member can quickly see what tasks have been moved to the “Done” column within the past week, providing a clear view of completed work.
- Gantt Chart (Option A): While useful for project scheduling and timeline visualization, Gantt charts are not typically used in Agile methodologies like Scrumban. They are more common in traditional project management approaches and don’t offer the same real-time, flexible view of work progress that a Kanban chart does.
- Feature Chart (Option B): This term is not commonly used in Agile or Scrumban contexts. It might refer to a chart showing the status of features, but it’s not a standard tool for tracking weekly work completion in Scrumban.
- Burndown Chart (Option D): While burndown charts are used in Scrum to track progress within a sprint, they are not the primary tool for viewing completed work in Scrumban. Burndown charts show remaining work over time, rather than explicitly showing completed tasks.
The Kanban chart is ideal for Scrumban teams because it:
- Provides a visual representation of work flow
- Allows for easy identification of completed tasks
- Supports continuous flow of work, which is a key principle in Scrumban
- Enables team members to quickly assess progress and identify bottlenecks
In conclusion, for a Scrumban team member wanting to know what work has been completed in a given week, the Kanban chart (option C) is the most appropriate and effective tool to review.