Question 41
During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?
A. Ishikawa diagram
B. Scatter diagram
* C. Pareto chart
D. Decision tree
Explanation
The Pareto chart should be used to identify the most important causes of issues during a quality analysis review. The Pareto chart is a graphical representation of the frequency and impact of different causes, helping to identify the most common and impactful causes.
Question 42
A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps.
Which of the following is the current status of the process?
A. Based on the rule of seven, the process is under control.
B. The amount of data is insufficient to determine if quality is low.
* C. The process is out of control and should be revised.
D. The goal should be adjusted since most of the data points are close to the lower limit.
Question 43
Which of the following is an activity that should be used in the closing phase of a project to support the project triple constraint?
* A. Evaluating the project
B. Releasing the resources
C. Closing the contracts
D. Reconciling the budget
Explanation
Evaluating the project is an activity that should be used in the closing phase of a project to support the project triple constraint. This involves reviewing the project plan, deliverables, and outcomes to ensure they meet the project objectives and requirements.
Question 44
A stakeholder works in a remote location and has not been replying to emails. The Internet service in that location is intermittent, and the stakeholder prefers to be contacted by telephone. Which of the following artifacts should the project manager have prepared to avoid this situation?
A. Responsibility assignment matrix
* B. Acceptable communication channels
C. Risk registry
D. Staff directory
Explanation
The project manager should have prepared acceptable communication channels to avoid the situation of a stakeholder not replying to emails due to intermittent Internet service. Acceptable communication channels are methods or modes of communication that are agreed upon by all parties involved in a project. They may include aspects such as email, phone call, text message, video conference, instant message, or face-to-face meeting. Acceptable communication channels can help to ensure that messages are delivered and received effectively and efficiently and that communication preferences and limitations are respected.
Question 45
Following a successful release, a project manager sent a survey to all stakeholders to gain an understanding of opportunity areas for the team. Which of the following can use the survey results as an input?
A. Daily stand-up
B. Project momentum
* C. Performance feedback
D. Meeting minutes
Explanation
The project manager can use the survey results as an input for performance feedback for the project team members. Performance feedback is a process of providing constructive and timely information on the performance of individuals or teams in relation to project goals and expectations.
Performance feedback can help to motivate, improve, and recognize project team members. The survey results can be used as an input for performance feedback. Performance feedback involves analyzing and evaluating the performance of the project team and project management against the project plan, including identifying areas for improvement. The survey results can help identify these areas for improvement and provide feedback to the project team on their performance.
Question 46
Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?
A. Social engineering
* B. Phishing
C. Spoofing
D. Hacking
Explanation
Phishing is a scenario where someone claiming to be from a legitimate organization sends an email or other message to a target person asking for sensitive information or access to a system or account. Phishing is a type of cyberattack that aims to trick the target into revealing personal or financial data or installing malware on their device. Phishing can compromise the security and privacy of the target and expose them to identity theft, fraud, or other malicious activities.
Question 47
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization’s reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Choose two.)
A. Train users on the proper use of the system.
B. Escalate the issue to the CCB.
* C. Hold sessions to understand user challenges.
D. Track system usage and report user activity.
* E. Log the issue in the project risk register.
F. Create a memorandum of acceptable use.
Explanation
The project manager should hold sessions to understand user challenges and track system usage and report user activity. These steps will help the project manager to identify the root causes of the adoption issues and monitor the progress of the system utilization. They will also help to communicate with the sales organization and provide feedback and support.
Question 48
A project manager has been assigned to a new project. During the planning phase, the project manager needs to get an understanding of the purpose of the project. Which of the following should the project manager do?
A. Collate the lessons learned.
B. Perform a gap analysis.
* C. Review existing artifacts.
D. Conduct a retrospective.
Explanation
The project manager should review existing artifacts to get an understanding of the purpose of the project.
Existing artifacts are documents or records that provide information about the project background, context, scope, objectives, requirements, stakeholders, and deliverables. They may include documents such as project proposal, project charter, business case, feasibility study, statement of work (SOW), or contract. Reviewing existing artifacts can help to clarify the project vision and expectations and provide a basis for planning and executing the project.
Question 49
DRAG DROP –
During a gate review meeting, the deliverable was rejected by the customer.
Review the dashboard.
Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.
Part 2: Select the proper document(s) to be updated.
Answer:
Explanation
Part 1:
Change Control Process:
- Consult the RACI matrix.
- Define new requirements and record changes.
- Assess the schedule, risk, and cost.
- Perform a demonstration.
- Obtain a sign off.
- Update and test the deliverable.
- Make an announcement on the company portal.
The change control process is a sequence of steps that helps to manage and document any changes or modifications to a project scope, schedule, cost, quality, or resources. The change control process typically involves the following steps:
- Consult the RACI matrix. A RACI matrix is a tool that defines and clarifies the roles and responsibilities of each team member for each task or activity in a project. RACI stands for responsible, accountable, consulted, and informed. Consulting the RACI matrix can help to identify who needs to be involved or informed about the change request and how to communicate with them.
- Define new requirements and record changes. The new requirements and changes are the details of what needs to be modified or added to the project deliverables or objectives based on the customer feedback or request. Defining and recording the new requirements and changes can help to communicate and justify the need and rationale for the change and its implications on the project scope and quality.
- Assess the schedule, risk, and cost. The schedule, risk, and cost are the aspects of the project that may be affected by the change request. Assessing the schedule, risk, and cost can help to determine the impact and feasibility of the change and identify any possible alternatives or corrective actions to minimize or avoid its negative effects.
- Perform a demonstration. A demonstration is a presentation or show of how the modified or updated deliverable works or meets the customer expectations or requirements. Performing a demonstration can help to validate and verify that the change request has been implemented correctly and effectively and to obtain feedback or approval from the customer or stakeholders.
- Obtain a sign off. A sign off is a formal acceptance and approval of the change request and its deliverables from the customer or stakeholders. Obtaining a sign off can help to confirm that the change request has been completed successfully and satisfactorily and to close the change control process.
- Update and test the deliverable. The deliverable is the product or service that is produced or provided by the project. Updating and testing the deliverable can help to ensure that it meets the quality standards and criteria and that it works as expected after implementing the change request.
- Make an announcement on the company portal. The company portal is a platform or channel that allows internal communication and collaboration among employees within an organization. Making an announcement on the company portal can help to inform and update other team members or departments about the change request and its outcomes and to share any lessons learned or best practices from the change control process.
Part2:
- Risk register: A risk register is a document that identifies, analyzes, and records the potential risks or uncertainties that may affect a project. Updating the risk register can help to capture any new or modified risks that may arise from the change request and to plan and implement appropriate risk responses.
- Schedule: A schedule is a document that shows the planned start and end dates, durations, dependencies, and progress of each task or activity in a project. Updating the schedule can help to reflect any changes or adjustments to the project timeline or milestones that may result from the change request and to monitor and control the project performance and delivery.
- Statement of work: A statement of work (SOW) is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. Updating the SOW can help to document any changes or additions to the project scope or deliverables that may be requested or agreed upon by the customer or stakeholders and to ensure alignment and agreement on what needs to be done and how it will be done.
- Change log: A change log is a document that tracks and records any changes or modifications that are made to the project scope, schedule, cost, quality, or resources during a project. Updating the change log can help to document the change request, approval, implementation, and impact of each change and ensure traceability and transparency.
Question 50
Which of the following BEST illustrates how team members with different roles should interact on the team?
A. SOW
B. WBS
* C. RACI
D. PERT
Explanation
RACI is a tool that best illustrates how team members with different roles should interact on the team. RACI is an acronym that stands for responsible, accountable, consulted, and informed. RACI is a type of responsibility assignment matrix (RAM) that defines and clarifies the roles and responsibilities of each team member for each task or activity in a project. RACI can help to improve communication, collaboration, and accountability among team members and avoid confusion, duplication, or conflicts.