Question 31

A project manager realizes that a project will not be completed on time due to resource constraints. Which of the following actions should the project manager take NEXT?

* A. Trigger the contingency plan and communicate with the stakeholders.
B. Work with the functional managers to create a work-around.
C. Submit a change request to the change control board.
D. Transfer the risk by hiring a new vendor who was successful on a previous project.
E. Set up an escalation meeting with the sponsor.

Explanation

Submit a change request to the change control board. The project manager should submit a change request to the change control board (CCB) if they realize that the project will not be completed on time due to resource constraints. A change request is a formal proposal to modify any aspect of the project, such as scope, schedule, cost, quality, or resources. A change request must be submitted to the CCB, which is a group of stakeholders who are authorized to review and approve changes. Submitting a change request can help to document the impact of the resource constraints on the project and seek approval for any corrective actions or preventive actions.

Question 32

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?

* A. Exploit the risk.
B. Accept the risk.
C. Avoid the risk.
D. Transfer the risk.

Explanation

The project manager should exploit the risk after an opportunity emerged in the middle of a project life cycle.

Exploit is a risk response strategy that aims to increase the probability and/or impact of a positive risk or opportunity. Exploit can involve actions such as allocating more resources, changing the scope or schedule, or adding more features or benefits to the project deliverables. Exploit can help to ensure that the opportunity is realized and that the project gains more value or advantage from it.

Question 33

As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?

A. Update the work breakdown structure.
B. Review the backlog.
* C. Seek baseline approval.
D. Establish the resource pool.

Explanation

The next step in the process after defining tasks, durations, resources, and costs is to seek baseline approval. A baseline is an approved version of a project plan that serves as a reference point for measuring progress and performance throughout the project lifecycle. A baseline typically includes scope, schedule, cost, quality, and risk parameters. Seeking baseline approval involves presenting the project plan to key stakeholders and obtaining their formal agreement on the project objectives and deliverables. Baseline approval can help to establish clear expectations, avoid scope creep, and facilitate change control during project execution.

The NEXT step after defining tasks, durations, resources, and costs during the planning phase is to seek baseline approval. Baseline approval involves finalizing the project plan and gaining approval from stakeholders, establishing the plan as the baseline for the project’s performance.

Question 34

An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

A. Which of the following MOST likely represents the observed relationship in this scenario? AB. Which of the following MOST likely represents the observed relationship in this scenario? B* C. Which of the following MOST likely represents the observed relationship in this scenario? CD. Which of the following MOST likely represents the observed relationship in this scenario? D

Explanation

Option C shows a graph that most likely represents the observed relationship in this scenario. The graph shows a learning curve, which is a graphical representation of the relationship between a learner’s performance on a task and the number of attempts or time required to complete the task. The learning curve theory proposes that a learner’s efficiency in a task improves over time the more the learner performs the task. In this case, the IT intern was able to complete more set-ups in less time as they gained more experience and proficiency over the two-week rotation.

Question 35

A project manager prefers to have immediate contact with team members because it allows for faster response times and more interactive discussions. Which of the following communication methods should the project manager use?

* A. Synchronous
B. Informal
C. Asynchronous
D. Formal

Explanation

The project manager should use synchronous communication methods if they prefer to have immediate contact with team members. Synchronous communication is a type of communication that occurs in real time and allows for faster response times and more interactive discussions. Examples of synchronous communication methods include phone calls, video conferences, instant messaging, and face-to-face meetings. Synchronous communication can help to build rapport, clarify doubts, and resolve issues quickly among team members.

Synchronous communication should be used when the project manager prefers to have immediate contact with team members. Synchronous communication allows for real-time interaction and feedback, enabling faster response times and more interactive discussions.

Question 36

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?

A. Document the request in the change control log.
* B. Communicate the change deployment.
C. Conduct an impact assessment.
D. Implement the change.

Explanation

The project manager should communicate the change deployment next after updating the project plan with the newest project end date as a result of an approved change. Communicating the change deployment involves informing all relevant parties about when and how the change will be implemented and what are the expected outcomes and benefits. Communicating the change deployment can help to ensure alignment, readiness, and support for the change and avoid any confusion or resistance.

Question 37

A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

A. Status report
B. Project plan
C. Change log
* D. Meeting minutes

Explanation

Meeting minutes should be prepared to ensure team members who are absent remain informed about assignments. Meeting minutes document what was discussed, decisions made, and assignments given during a meeting, providing a record of the team’s progress and ensuring absent members are up-to-date.

The project manager should prepare meeting minutes to ensure team members who are absent remain informed about assignments. Meeting minutes are a written record of what was discussed and decided in a meeting. They usually include information such as attendees, agenda items, action items, decisions made, issues raised, and deadlines assigned. Meeting minutes can help to communicate important information to team members who could not attend the meeting and provide a reference for future follow-up.

Question 38

Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?

* A. Communicate with the affected stakeholders.
B. Initiate a formal change request to modify the cost.
C. Adjust the scope to stay within the cost.
D. Set a new cost using a lightweight estimation method.

Explanation

The project manager should communicate with the affected stakeholders first after realizing that the sign-off for the project scope baseline is delayed due to multiple changes and that the budget for this project is restricted by the project sponsor. The affected stakeholders are those who have an interest or influence on the project and may be impacted by any changes or delays. Communicating with them can help to explain the situation, assess the impact, seek feedback, and manage expectations.

Question 39

Which of the following BEST describes how an organization should coordinate management of multiple related projects?

A. Apply the SDLC process.
* B. Establish a program.
C. Consult the CCB.
D. Use different frameworks.

Explanation

The BEST way to coordinate management of multiple related projects is to establish a program. A program is a group of related projects that are managed together to achieve specific strategic business objectives.

The organization should establish a program to coordinate management of multiple related projects. A program is a group of related projects, subprograms, and program activities that are managed in a coordinated way to obtain benefits and control not available from managing them individually. A program can help to align multiple projects with strategic goals, optimize resources and risks, and deliver value to stakeholders.

Question 40

After a release, the project sponsor received an escalation from an executive about the extension of the downtime after the scheduled window. Which of the following should be added to the issue log?

A. Continuous integration
B. Rollback plan
* C. Customer notification
D. Automated testing

Explanation

Customer notification should be added to the issue log after receiving an escalation from an executive about the extension of the downtime after the scheduled window. Customer notification is a communication activity that informs the customers about any issues or changes that may affect their satisfaction or expectations.

Customer notification can help to maintain trust, transparency, and goodwill with the customers and prevent any negative impacts on their business operations or experience.