What Does Float Mean in Project Management?

Understanding Total Float vs. Free Float in Construction Project Schedules

Learn the exact definition of float in project management. Understand how float (or slack) determines the amount of time a task can be delayed without impacting the final project deadline and why it is essential for schedule flexibility.

Question

You are managing a construction project with a strict deadline. While reviewing your project’s schedule, you notice that certain tasks have some flexibility in their start and finish dates. You also realize that there is a possibility to delay certain tasks without affecting the overall project timeline. In this context, what does the term “float” refer to?

A. The amount of time a task can be delayed without impacting the project’s finish date
B. The total number of tasks that need to be completed before the project deadline
C. The cost of resources required to complete a task within the schedule

Answer

A. The amount of time a task can be delayed without impacting the project’s finish date

Explanation

In project management, “float” (also widely known as “slack”) represents the built-in flexibility or buffer time within a project schedule. Specifically, total float is the amount of time that an individual task can be delayed from its early start date without causing any delay to the final, overall project completion date. Understanding and calculating float is a critical component of the Critical Path Method (CPM), as it allows project managers to identify which tasks have scheduling leeway and which tasks (those on the critical path with zero float) must be strictly managed to ensure the project is delivered on time.