Question
Which role represents the stakeholders who will operate the project’s products after the project is complete?
A. Executive
B. Senior user
C. Senior supplier
D. Project manager
Answer
B. Senior user
Explanation
In PRINCE2, the Senior User is responsible for representing the interests of those who will use the project’s products, including operations and maintenance. They ensure that user needs are specified correctly and that the solution meets those needs.
The Senior User commits user resources, specifies the benefits and expected outcomes, and ensures the desired outcome is achieved. They are responsible for user liaison throughout the project.