Discover which PMP process group focuses on producing deliverables during project execution. Learn about its importance and role in project management success.
Table of Contents
Question
In a project status report, the project manager mentions the deliverables produced during the execution phase. Which process group does this output primarily belong to?
A. Initiating – Deliverables are identified and defined at the beginning of the project.
B. Planning – Deliverables are planned, but not yet produced, in this phase.
C. Executing – Deliverables are created as part of the project work during this phase.
D. Monitoring and Controlling – Deliverables are monitored and adjusted to ensure they meet project requirements.
Answer
C. Executing – Deliverables are created as part of the project work during this phase.
Explanation
The correct answer is C. Executing. In project management, deliverables are produced during the Executing process group. This stage involves implementing the project plan, where the actual work is carried out to achieve the project’s objectives. Deliverables, whether tangible or intangible, are outputs of the project work conducted by the team under the guidance of the project manager.
Deliverables Defined: Deliverables are the completed results or outputs of project tasks. They are not created during the Planning phase, where the scope and schedule are prepared, nor during the Monitoring and Controlling phase, which focuses on ensuring the deliverables align with the requirements and objectives.
Key Activities in Executing:
- Coordinating resources and team efforts to carry out the project plan.
- Producing deliverables per the project scope and requirements.
- Managing stakeholder expectations and communication.
Other Process Groups:
- Initiating: Establishes project objectives and stakeholders but does not produce deliverables.
- Planning: Develops plans for deliverables but does not create them.
- Monitoring and Controlling: Ensures the quality and progress of deliverables but does not create them.
For successful PMP exam preparation, understanding the distinct roles of process groups is crucial, as questions often test your ability to differentiate between them.
The creation of deliverables is an essential activity within the Executing process group. During this phase, the project team performs the work defined in the project management plan to produce the deliverables as outlined in the scope. The Monitoring and Controlling process group, while important for tracking and ensuring that deliverables meet quality standards, focuses on performance and changes rather than the direct creation of deliverables.
In contrast, the Initiating and Planning process groups focus on defining and planning the project, respectively, but the actual production of deliverables occurs during execution.
PMI PMP certification exam assessment practice question and answer (Q&A) dump including multiple choice questions (MCQ) and objective type questions, with detail explanation and reference available free, helpful to pass the PMI PMP exam and earn PMI PMP certification.