PMI PMP: How to Handle Impediments in the Product Backlog

Learn how to answer a PMP exam question about what the product owner should do when the team faces impediments in the product backlog.

Question

A product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments.

What should the project manager suggest that the product owner do next?

A. Ensure that the impediments are captured and prioritized based upon the highest valued features
B. Estimate the financial impact of the impediments and request additional funding
C. Begin to remove the impediments, starting with the easiest ones first, to foster team accomplishment
D. Capture the impediments and inform management that their assistance is needed in resolving the impediments

Answer

A. Ensure that the impediments are captured and prioritized based upon the highest valued features

Explanation

The product owner is responsible for maximizing the value of the product and the work of the development team. One of the ways to do this is to ensure that the product backlog is visible, transparent, and clear to all, and shows what the team will work on next. The product owner also needs to order the items in the product backlog to best achieve goals and missions. Therefore, if the team faces some impediments that affect the implementation of some features, the product owner should capture and prioritize them based on the highest valued features. This way, the product owner can collaborate with the team and other stakeholders to resolve the impediments and deliver the most valuable product increment.

Reference

Project Management Professional PMI-PMP certification exam practice question and answer (Q&A) dump with detail explanation and reference available free, helpful to pass the Project Management Professional PMI-PMP exam and earn Project Management Professional PMI-PMP certification.