Learn how to use the iteration review, a regular event in agile projects, to show the business stakeholders how the feature integration works and get their feedback.
Table of Contents
Question
A project manager is leading a product feature rollout that will gain more subscribers for a video-streaming application. During the backlog grooming phase. the business stakeholders were unable to understand the feature integration with the product and raised concerns.
What can the project manager do to demonstrate the feature integration?
A. Include the business stakeholders in the iteration review.
B. Involve business stakeholders in the iteration retrospective.
C. Create a task for the iteration review and add it to the backlog.
D. Review the backlog in detail with the business stakeholders.
Answer
A. Include the business stakeholders in the iteration review.
Explanation
The iteration review is a regular event where the team inspects the increment at the end of every iteration to assess progress, and then adjusts its backlog for the next iteration. During the iteration review, the team demonstrates the significant new behavior and knowledge gained from the iteration’s completed stories, and receives feedback from the product owner and other stakeholders. This is the best way for the project manager to show the business stakeholders how the feature integration works and address their concerns. The other options are not as effective because:
- B. The iteration retrospective is where the team members discuss the results of the iteration, review their practices, and identify ways to improve. This is not the appropriate event to demonstrate the feature integration to the business stakeholders, as it is focused on the team’s process improvement rather than the product’s functionality.
- C. Creating a task for the iteration review and adding it to the backlog is not necessary, as the iteration review is a standard event that occurs at the end of every iteration. Moreover, this does not ensure that the business stakeholders will attend the iteration review or understand the feature integration.
- D. Reviewing the backlog in detail with the business stakeholders may help them understand the scope and priority of the feature integration, but it does not demonstrate how it works in the product. The backlog is a list of user stories and acceptance criteria, not a working, tested increment.
Reference
Project Management Professional PMI-PMP certification exam practice question and answer (Q&A) dump with detail explanation and reference available free, helpful to pass the Project Management Professional PMI-PMP exam and earn Project Management Professional PMI-PMP certification.