MB-330: How to Handle Delays in Master Planning for Microsoft Dynamics 365 SCM?

Learn the top 3 actions to manage delays effectively in Microsoft Dynamics 365 Supply Chain Management’s master planning module. Discover how to prevent cascading delays and optimize production with proper BOM delay management.

Table of Contents

Question

You are tasked with setting up the master planning module in Microsoft Dynamics 365 Supply Chain Management. The company has a complex production setup with various BOM levels, and they frequently encounter delays due to material and capacity constraints.
You need to ensure that delays at lower BOM levels are reflected accurately in the master planning run to prevent cascading delays across the production process.
What three actions should you perform? Each correct answer presents part of the solution. Choose 3.

A. Approve or firm the production orders at the top of the BOM structure with delays prior to the next master planning run.
B. Use action messages to identify and adjust the dates of planned orders that can be moved due to delays in the BOM structure.
C. Configure the coverage group settings to calculate delays for each item attached to the group.
D. Increase the lead times for lower-level BOM items to manually account for potential delays.
E. Disable the delay calculation feature in the Master planning parameters page.
F. Set the start time for the calculation of delays to a future date to avoid immediate delay recognition.

Answer

A. Approve or firm the production orders at the top of the BOM structure with delays prior to the next master planning run.
B. Use action messages to identify and adjust the dates of planned orders that can be moved due to delays in the BOM structure.
C. Configure the coverage group settings to calculate delays for each item attached to the group.

Explanation

Option A is correct because approving or firming the production orders at the top of the BOM structure ensures that delays are kept and all underlying components are updated accordingly. Option B is correct as action messages help in identifying and adjusting the dates of planned orders affected by delays. Option C is correct because configuring the coverage group settings to calculate delays ensures that delays are calculated for each item in the group. Option D is incorrect because increasing lead times does not address the issue of delays not being applied to all items in the BOM structure. Option E is incorrect as disabling the delay calculation feature would prevent any delays from being calculated, which is not the goal. Option F is incorrect because setting the start time for the calculation of delays to a future date would not solve the problem of delays not being applied to all items immediately.

Microsoft Dynamics 365 Supply Chain Management Functional Consultant MB-330 certification exam assessment practice question and answer (Q&A) dump including multiple choice questions (MCQ) and objective type questions, with detail explanation and reference available free, helpful to pass the Microsoft Dynamics 365 Supply Chain Management Functional Consultant MB-330 exam and earn Microsoft Dynamics 365 Supply Chain Management Functional Consultant MB-330 certification.