In Which Risk Management Process Do You First Document Risks in the Risk Register?

Identify Risks Process: When Does the Risk Register Get Populated in Projects?

Understand the Identify Risks process in project management and its key role in initially documenting identified risks into the risk register. Learn the sequence of risk management processes for exam success.

Question

You are managing a project and have just completed a risk identification session with your team. During this session, various risks were discussed and recorded. You now need to formally document the identified risks in the project management plan. In which project management process will you use a risk register to document the identified risks?

A. Plan Risk Management
B. Monitor Risks
C. Identify Risks

Answer

C. Identify Risks

Explanation

The Identify Risks process is where the project team formally documents newly identified risks in the risk register for the first time, capturing details such as risk descriptions, potential causes, categories, and initial triggers. This process follows the planning of the overall risk management approach (Plan Risk Management) and precedes risk analysis and response planning. The risk register serves as the living repository that gets updated iteratively throughout later processes like analysis, response planning, and monitoring, but its initial population occurs during risk identification.