Question
You are managing a project and need to determine the longest sequence of dependent tasks, as well as their durations, to ensure the project is completed on time. You are considering different methods to help you identify critical tasks and their potential impacts on the overall timeline. In this scenario, which project management technique will help you identify the longest sequence of dependent tasks and determine the minimum project duration?
A. Earned Value Management (EVM)
B. Critical Path Method (CPM)
C. Resource Leveling
Answer
B. Critical Path Method (CPM)
Explanation
The Critical Path Method (CPM) is an essential technique in project management used to map out the longest sequence of dependent activities required to complete a project. By analyzing task dependencies and calculating the earliest and latest possible start and finish times for each activity, CPM determines the minimum possible project duration. Tasks that fall on this critical path have zero float (or slack), meaning any delay in these specific tasks will directly result in a delay to the overall project timeline. This method provides project managers with a clear visualization of critical tasks, allowing them to prioritize resources and proactively mitigate potential scheduling bottlenecks.