Question
You are managing a hybrid project that combines both predictive and agile approaches. The client has provided high-level requirements but emphasizes the need for flexibility to adapt to changing priorities during the project. During a team meeting, a junior team member asks, “How should we define the project scope to balance flexibility and control in this hybrid environment?”
A. Use a high-level scope for the predictive components while iteratively refining details for agile components.
B. Define the entire scope upfront and stick to it rigidly to avoid scope creep.
C. Avoid defining the scope altogether to allow maximum flexibility.
Answer
A. Use a high-level scope for the predictive components while iteratively refining details for agile components.
Explanation
In a hybrid project environment, a high-level scope establishes the overall boundaries and strategic vision, which is essential for managing the predictive (plan-driven) elements of the project, such as broad timelines, budget estimates, and fixed dependencies. However, for the agile (adaptive) components, this high-level scope is intentionally left flexible, allowing the team to iteratively elaborate and refine the detailed requirements through product backlogs, sprint planning, and continuous stakeholder feedback. This approach balances the need for upfront structure and governance with the agility required to adapt to changing client priorities or market conditions as the project progresses.