Question
You are assigned as a project manager for a software development project. During the first team meeting, stakeholders provide conflicting expectations about deliverables. Some want additional features included without extending the timeline.
What should be your first step?
A. Ignore conflicting requirements and proceed with the initial plan.
B. Conduct a detailed requirements gathering session and document the agreed-upon scope.
C. Immediately add all requested features to the project plan to satisfy stakeholders.
Answer
B. Conduct a detailed requirements gathering session and document the agreed-upon scope.
Explanation
When stakeholders present conflicting expectations—such as requesting additional features without altering the timeline—the project manager must first conduct a thorough requirements gathering session to understand and align all needs. Ignoring the conflict leads to stakeholder dissatisfaction and misalignment with business goals, while immediately accepting all requests guarantees scope creep and inevitable project failure due to schedule and budget overruns. By documenting and negotiating an agreed-upon scope baseline, the project manager creates a realistic, achievable plan that balances stakeholder demands with the project’s actual constraints.