Question

A VxRail Test Plan has been completed. What is the protocol for recording the results?

A. With the implementation team, complete each test and document the test date
B. With the implementation team, complete and document each test, test date, and a screenshot of results
C. In front of a customer, complete and document each test, test date, and a screenshot of results
D. In front of a customer, complete each test and document the test date

Answer

B. With the implementation team, complete and document each test, test date, and a screenshot of results

Explanation

After completing a VxRail Test Plan, it is important to follow the proper protocol for recording the results. The protocol is as follows:

B. With the implementation team, complete and document each test, test date, and a screenshot of results.

This option ensures that the test results are accurate, consistent, and verifiable. It also allows the implementation team to troubleshoot any issues that may arise during the testing process. The documentation should include the name of the test, the date it was performed, and a screenshot of the results. The screenshot should show the relevant information and metrics that demonstrate the success or failure of the test. The documentation should be stored in a secure location that can be accessed by the customer and the implementation team.

The VxRail Test Plan is a document that outlines the tests that will be performed to verify the functionality of a VxRail cluster. The test plan should be completed by the implementation team in collaboration with the customer. The test plan should include the following information:

  • The tests that will be performed
  • The expected results of each test
  • The date and time that each test was performed
  • A screenshot of the results of each test

The test plan should be updated as needed to reflect changes to the VxRail cluster. The test plan should be stored in a secure location and should be accessible to the implementation team and the customer.

The other options are incorrect for various reasons:

A. With the implementation team, complete each test and document the test date.

This option is incomplete because it does not include a screenshot of the results. A screenshot is necessary to provide evidence of the test outcome and to avoid any disputes or misunderstandings.

C. In front of a customer, complete and document each test, test date, and a screenshot of results.

This option is inappropriate because it exposes the customer to potential errors or failures that may occur during the testing process. It also puts pressure on the implementation team and may affect their performance. The testing process should be done internally by the implementation team before presenting the final results to the customer.

D. In front of a customer, complete each test and document the test date.

This option is both incomplete and inappropriate because it does not include a screenshot of the results and it involves performing the tests in front of the customer. As explained above, both of these aspects are undesirable and unprofessional.

Reference

Dell Specialist – Implementation Engineer, VxRail DES-6322 certification exam practice question and answer (Q&A) dump with detail explanation and reference available free, helpful to pass the Dell Specialist – Implementation Engineer, VxRail DES-6322 exam and earn Dell Specialist – Implementation Engineer, VxRail DES-6322 certification.