PL-400: Which Event Framework Stage Should You Use to Modify Message Values in Dataverse?

How to Choose the Correct Stage for Custom Code Execution in Dataverse Event Pipeline?

Table of Contents

Question

An organization uses Microsoft Dataverse.

You must implement custom code by using the Event framework. The code must run in response to specific Microsoft Dataverse events. Tables operations are handled by using messages.

At which stage should you register a step to change any value included in messages?

Select only one answer.

A. PreValidation
B. PreOperation
C. MainOperation
D. PostOperation

Answer

B. PreOperation

Explanation

This item tests the candidate’s knowledge of how to configure events by using the plug-in registration tool.

If you want to change any values for an entity included in messages, you should do it in the PreOperation stage. The PreValidation. MainOperation, and PostOperation stages cannot be used to change any values included in messages.