Question
The Team Manager has received notification that the new hardware and software solution has been installed and completed, but there is a concern that it has not been approved by the appropriate people.
Which 2 actions should the Team Manager take to check that the completed products have been approved as required?
A. Check the Work Package to ascertain who should approve the completed Work Package.
B. Check the Product Descriptions to ascertain who should have approved the products.
C. Check the Configuration Management Strategy for product handover procedures.
D. Check the approval records as required in the Work Package.
E. Check the Product Descriptions for the quality method required.
Answer
B. Check the Product Descriptions to ascertain who should have approved the products.
D. Check the approval records as required in the Work Package.
Explanation
Product Descriptions define the quality criteria, quality methods, and quality responsibilities for each product, including who should approve the product. By reviewing the Product Descriptions, the Team Manager can determine the appropriate approvers for the completed products.
The Work Package contains information on the approval records required for the products created as part of the work package. The Team Manager should review these approval records to confirm that the necessary approvals have been obtained in accordance with the Work Package requirements.