Question 61: The ways in which the roles and responsibilities, reporting relationships, and staffing management will be addressed and structured within a project is described in the:

A. Human resource management plan.
B. Activity resource requirements.
C. Personnel assessment tools,
D. Multi-criteria decision analysis.

Question 62: The process of identifying and documenting relationships among the project activities is known as:

A. Control Schedule.
B. Sequence Activities.
C. Define Activities.
D. Develop Schedule.

Question 63: Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:

A. Enterprise environmental factors
B. Work performance reports
C. Organizational process assets
D. Context diagrams

Question 64: The organization’s perceived balance between risk taking and risk avoidance is reflected in the risk:

A. Responses
B. Appetite
C. Tolerance
D. Attitude

Question 65: An output of the Manage Stakeholder Engagement process is:

A. change requests
B. enterprise environmental factors
C. the stakeholder management plan
D. the change log

Question 66: Which process numerically analyzes the effect of identified risks on overall project objectives?

A. Plan Risk Management
B. Plan Risk Responses
C. Perform Quantitative Risk Analysis
D. Perform Qualitative Risk Analysis

Question 67: An input to the Plan Procurement Management process is:

A. Source selection criteria.
B. Market research.
C. A stakeholder register.
D. A records management system.

Question 68: Reserve analysis is a tool and technique used in which process?

A. Plan Risk Management
B. Plan Risk Responses
C. Identify Risks
D. Control Risks

Question 69: Updates to organizational process assets such as procurement files, deliverable acceptances, and lessons learned documentation are typical outputs of which process?

A. Close Project or Phase
B. Conduct Procurements
C. Control Procurements
D. Close Procurements

Question 70: Risk categorization is a tool or technique used in which process?

A. Plan Risk Responses
B. Plan Risk Management
C. Perform Qualitative Risk Analysis
D. Perform Quantitative Risk Analysis