Over 600 PMI Certified Associate in Project Management (CAPM) Exam Questions and Answers

Question 51: Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?

A. Bottom-up
B. Parametric
C. Analogous
D. Three-point

Question 52: Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

A. Direct
B. Interactive
C. Pull
D. Push

Question 53: A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

A. Identify Risks
B. Control Risks
C. Perform Quantitative Risk Analysis
D. Perform Qualitative Risk Analysis

Question 54: Which Knowledge Area involves identifying the people, groups, or organizations that may be impacted by or impact a project?

A. Project Risk Management
B. Project Human Resource Management
C. Project Scope Management
D. Project Stakeholder Management

Question 55: Which process identifies whether the needs of a project can best be met by acquiring products, services, or results outside of the organization?

A. Plan Procurement Management
B. Control Procurements
C. Collect Requirements
D. Plan Cost Management

Question 56: The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

A. Work packages.
B. Accepted deliverables.
C. The WBS dictionary.
D. The scope baseline.

Question 57: The ability to influence cost is greatest during which stages of the project?

A. Early
B. Middle
C. Late
D. Completion

Question 58: Which tool or technique is used in the Develop Project Management Plan process?

A. Project management information system (PMIS)
B. Project charter
C. Quality assurance
D. Expert judgment

Question 59: Lessons learned are created and project resources are released in which Process Group?

A. Planning
B. Executing
C. Closing
D. Initiating

Question 60: A key benefit of the Manage Communications process is that it enables:

A. The best use of communication methods.
B. An efficient and effective communication flow.
C. Project costs to be reduced.
D. The best use of communication technology.