Question 581: For the given information:

Activity A, duration 5 days, predecessors: none
Activity B, duration 3 days, predecessors: none
Activity C, duration 6 days, predecessors: A and B
Activity D, duration 7 days, predecessors: B
Activity E, duration 4 days, predecessors: C and D
Activity F, duration 2 days, predecessors: E and B
Which of the following shows the project’s critical path?

A. Start, B, F, Finish
B. Start, B, C, E, F, Finish
C. Start, B, D, E, F, Finish
D. Start, A, C, E, F, Finish

Question 582: The primary purpose of the stakeholder register is to:

A. Record stakeholder issues on the project
B. Maintain lessons learned earlier in the project
C. Maintain a list of all project stakeholders
D. Document change requests and their status

Question 583: Work performance information is an input to which of the following processes?

A. Direct and Manage Project Work
B. Monitor and Control Project Work
C. Control Scope
D. Validate Scope

Question 584: What can the project manager find among the factors that could lead a project to be tailored?

A. Company culture
B. Return on investment
C. Earned Value
D. Schedule Performance Index

Question 585: Project managers play a key role in performing integration on a project. What are the three different levels of integration?

A. Process, cognitive, and context
B. Complexity, understand, and change
C. Interact, insight, and leadership
D. Communication, knowledge, and value

Question 586: Using the following information and assuming that the project team will work a standard 40-hour work week:
Activity A has a duration of 10 days.
Activity B has a duration of 10 days and its predecessor is Activity A.
Activity C has a duration of 15 days and its predecessor is Activity A.
Activity D has a duration of 10 days and its predecessor is Activity B and C.
Activity E has a duration of 10 days and its predecessor is Activity D.
Activity F has a duration of 15 days and its predecessor is Activity D.
What is the critical path of the project?

A. ABDE
B. ACDF
C. ABDF
D. ACDE

Question 587: Recognition and rewards are tools and techniques of which process?

A. Develop Team
B. Manage Team
C. Control Resources
D. Plan Resource Management

Question 588: At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?

A. Create Work Breakdown Structure (WBS)
B. Create Scope Baseline
C. Collect Requirements
D. Define Scope

Question 589: A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

A. Informal communication
B. Internal communication
C. Formal communication
D. Horizontal communication

Question 590: A project manager is launching an information system to provide a lessons learned database. This action is necessary for recipients to access content at their own discretion. Which communication method is described?

A. Push communication
B. Pull communication
C. Interactive communication
D. Stakeholder communication