Over 600 PMI Certified Associate in Project Management (CAPM) Exam Questions and Answers

Question 41: The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:

A. Collect Requirements.
B. Conduct Procurements.
C. Estimate Activity Durations.
D. Estimate Activity Resources.

Question 42: Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?

A. Procurement documents
B. Communications plan
C. Project charter
D. Stakeholder register

Question 43: Which process determines the risks that may affect the project and documents their characteristics?

A. Control Risks
B. Plan Risk Management
C. Plan Risk Responses
D. Identify Risks

Question 44: An example of a group decision-ma king technique is:

A. Nominal group technique.
B. Majority.
C. Affinity diagram.
D. Multi-criteria decision analysis.

Question 45: A risk response strategy in which the project team shifts the impact of a threat, together with ownership of the response, to a third party is called:

A. mitigate
B. accept
C. transfer
D. avoid

Question 46: An output of the Plan Quality Management process is:

A. A process improvement plan.
B. Quality control measurements.
C. Work performance information.
D. The project management plan.

Question 47: A project manager should document the escalation path for unresolved project risks in the:

A. Change control plan
B. Stakeholder register
C. Risk log
D. Communications management plan

Question 48: Which process in Project Time Management includes reserve analysis as a tool or technique?

A. Estimate Activity Resources
B. Sequence Activities
C. Estimate Activity Durations
D. Develop Schedule

Question 49: Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:

A. Expert judgment.
B. Analytical techniques.
C. Earned value management.
D. Group decision-making techniques.

Question 50: When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?

A. Negative
B. Zero
C. Positive
D. Free