Question 451: What is the minimum a project schedule must include?

A. Variance analysis
B. A planned start date and a planned finish date for each schedule activity
C. A critical path diagram
D. Critical chain analysis

Question 452: What process determines which risks might affect the project?

A. Qualitative risk analysis
B. Identify Risks
C. Plan Risk Management
D. Quantitative risk analysis

Question 453: What scope definition technique is used to generate different approaches to execute and perform the work of the project?

A. Build vs. buy
B. Expert judgment
C. Alternatives identification
D. Product analysis

Question 454: When a control chart is used to monitor performance of a process, which of the following will be set by the project manager and the appropriate stakeholders to reflect the point(s) at which corrective action will be taken to prevent exceeding the specification limits?

A. Upper and lower control limits
B. Upper and lower specification limits
C. Process mean
D. Data points

Question 455: Which Activity Duration Estimating technique incorporates additional timing for contingency purposes?

A. Analogous Estimating
B. Expert Judgment
C. Optimistic Estimates
D. Reserve Analysis

Question 456: Which characteristic is unique to project work and does not apply to operational work?

A. Performed by individuals
B. Limited by constraints
C. Temporary
D. Performed to achieve organizational objectives

Question 457: Which document describes the procurement item in sufficient detail to allow prospective sellers to determine if they are capable of providing the products, services, or results?

A. Procurement management plan
B. Procurement statement of work
C. Request for proposal
D. Request for quote

Question 458: Which is an input to the Scope Verification Process?

A. Performance report
B. Work breakdown structure
C. Requested changes
D. Project scope statement

Question 459: Which is the document that presents a hierarchical project organization?

A. WBS
B. CPI
C. OBS
D. BOM

Question 460: Which knowledge area employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?

A. Project Risk Management
B. Project Integration Management
C. Project Communications Management
D. Project Quality Management