Over 600 PMI Certified Associate in Project Management (CAPM) Exam Questions and Answers

Question 381: Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

A. Cost Plus Award Fee Contract (CPAF)
B. Firm-Fixed -Price Contract (FFP)
C. Time and Material Contract (T&M)
D. Cost Plus Incentive Fee Contract (CPIF)

Question 382: During project selection, which factor is most important?

A. Types of constraints
B. Internal business needs
C. Budget
D. Schedule

Question 383: The staffing management plan is part of the:

A. organizational process assets.
B. resource calendar.
C. human resource plan.
D. Develop Project Team process.

Question 384: Which is an output of the Collect Requirements process?

A. Requirements traceability matrix
B. Project scope statement
C. WBS dictionary
D. Work performance measurements

Question 385: A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

A. Slack
B. Float
C. Lag
D. Lead

Question 386: The completion of the project scope is measured against the:

A. requirements documentation.
B. project scope statement.
C. project management plan.
D. work performance measurements.

Question 387: Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

A. Scope baseline
B. Scope management plan
C. Change management plan
D. Cost baseline

Question 388: The total of the planned value (PV) is also known as:

A. work breakdown structure (WBS).
B. schedule target.
C. performance measurement baseline (PMB).
D. earned value baseline.

Question 389: Plan-do-check-act is also known as:

A. prevention over inspection.
B. statistical sampling.
C. management responsibility.
D. continuous improvement.

Question 390: The risk shared between the buyer and seller is determined by the:

A. assumption log.
B. quality checklist.
C. risk register.
D. contract type.