Over 600 PMI Certified Associate in Project Management (CAPM) Exam Questions and Answers

Question 351: Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?

A. Exploit
B. Share
C. Enhance
D. Transfer

Question 352: A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?

A. There is a cost underrun.
B. There is a cost overrun.
C. The project may not meet the deadline
D. The project is 20 days behind schedule.

Question 353: What does a CPI value greater than 1.0 indicate?

A. Cost right at the estimated value
B. Cost under the estimated value
C. Cost right at the actual value
D. Cost over the estimated value

Question 354: Which of the following is an output from Control Scope?

A. Change requests
B. Variance analysis
C. Accepted deliverables
D. Requirements documentation

Question 355: Managing procurement relationships and monitoring contract performance are part of which process?

A. Conduct Procurements
B. Plan Procurements
C. Administer Procurements
D. Close Procurements

Question 356: Which of the following is an input to the Perform Qualitative Risk Analysis process?

A. Risk register
B. Risk data quality assessment
C. Risk categorization
D. Risk urgency

Question 357: The process of identifying the stakeholders’ information needs is completed during:

A. Plan Communications.
B. Manage Stakeholder Expectations.
C. Stakeholder Analysis.
D. Identify Stakeholders.

Question 358: What is the most accurate rough order of magnitude (ROM)?

A. In the Initiation phase, the estimate is in the range of +/- 50%.
B. In the Planning phase, the estimate is in the range of +/- 50%.
C. In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%.
D. In the Closing phase, the estimate is in the range of +/- 15%.

Question 359: Project contracts generally fall into which of the following three broad categories?

A. Fixed-price, cost reimbursable, time and materials
B. Make-or-buy, margin analysis, fixed-price
C. Time and materials, fixed-price, margin analysis
D. Make-or-buy, lump-sum, cost-plus-incentive

Question 360: Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

A. Applying calendars
B. Resource leveling
C. Resource planning
D. Resource conflict management