Question 281: Which of the following factors is lowest at the start of the project?

A. Cost of changes
B. Stakeholder influences
C. Risk
D. Uncertainty

Question 282: In which domain of project management would a Pareto chart provide useful information?

A. Project Scope Management
B. Project Time Management
C. Project Communications Management
D. Project Quality Management

Question 283: In which process might a project manager use risk reassessment as a tool and technique?

A. Perform Qualitative Risk Analysis
B. Monitor and Control Risk
C. Monitor and Control Project Work
D. Plan Risk Responses

Question 284: Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

A. WBS directory
B. Activity list
C. WBS
D. Project schedule

Question 285: Which process occurs within the Monitoring and Controlling Process Group?

A. Control Costs
B. Plan Quality
C. Perform Quantitative Risk Analysis
D. Determine Budget

Question 286: Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

A. Perform Quality Control
B. Quality Metrics
C. Perform Quality Assurance
D. Plan Quality

Question 287: How is the schedule variance calculated using the earned value technique?

A. EV less AC
B. AC less PV
C. EV less PV
D. AC less EV

Question 288: Which Perform Quality Control tool graphically represents how various elements of a system interrelate?

A. Control chart
B. Flowchart
C. Run chart
D. Pareto chart

Question 289: Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?

A. Project Time Management
B. Project Cost Management
C. Project Scope Management
D. Project Human Resource Management

Question 290: In which process is a project manager identified and given the authority to apply resources to project activities?

A. Acquire Project Team
B. Develop Project Management Plan
C. Manage Project Execution
D. Develop Project Charter