Over 600 PMI Certified Associate in Project Management (CAPM) Exam Questions and Answers

Question 201: Project or phase closure guidelines or requirements, historical information, and the lessons learned knowledge base are examples of which input to the Close Project or Phase process?

A. Organizational process assets
B. A work breakdown structure
C. The project management plan
D. Enterprise environmental factors

Question 202: The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

A. Supportive
B. Leading
C. Neutral
D. Resistant

Question 203: Which of the following is a narrative description of products, services, or results to be delivered by a project?

A. Project statement of work
B. Business case
C. Accepted deliverable
D. Work performance information

Question 204: A project manager seeking insight on previous stakeholder management plans and their effectiveness should evaluate:

A. Historical information and the lessons-learned database.
B. Historical information and the stakeholder register.
C. Organizational process assets and the lessons-learned database.
D. Project documents and historical information.

Question 205: Projects are undertaken by an organization to support the:

A. Product performance.
B. Budget process.
C. Collective capabilities.
D. Organizational strategy.

Question 206: What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

A. 0.45
B. 0.56
C. 0.70
D. 1.36

Question 207: The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:

A. start-to-start (SS)
B. start-to-finish (SF)
C. finish-to-start (FS)
D. finish-to-finish (FF)

Question 208: Work performance information and cost forecasts are outputs of which Project Cost Management process?

A. Estimate Costs
B. Plan Cost Management
C. Determine Budget
D. Control Costs

Question 209: Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?

A. Coaching
B. Avoidance
C. Consensus
D. Influencing

Question 210: The procurement process that documents agreements and related documentation for future reference is known as:

A. Plan Procurements.
B. Control Procurements.
C. Close Procurements.
D. Conduct Procurements.