Over 600 PMI Certified Associate in Project Management (CAPM) Exam Questions and Answers

Question 191: Requirements documentation will typically contain at least:

A. Stakeholder requirements, staffing requirements, and transition requirements.
B. Business requirements, the stakeholder register, and functional requirements.
C. Stakeholder impact, budget requirements, and communications requirements.
D. Business objectives, stakeholder impact, and functional requirements.

Question 192: Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?

A. Portfolio
B. Project
C. Program
D. Operations

Question 193: An input of the Plan Procurement Management process is:

A. Make-or-buy decisions.
B. Activity cost estimates.
C. Seller proposals.
D. Procurement documents.

Question 194: Which organizational process assets update is performed during the Close Procurements process?

A. Procurement audit
B. Lessons learned
C. Performance reporting
D. Payment requests

Question 195: The individual or group that provides resources and support for a project and is accountable for success is the:

A. sponsor
B. customer
C. business partners
D. functional managers

Question 196: A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:

A. budget at completion (BAC)
B. earned value management (EVM)
C. to-complete performance index
D. cost performance index

Question 197: A collection of projects managed as a group to achieve strategic objectives is referred to as a:

A. plan
B. process
C. program
D. portfolio

Question 198: Sharing good practices introduced or implemented in similar projects in the organization and/or industry is an example of:

A. quality audits
B. process analysis
C. statistical sampling
D. benchmarking

Question 199: When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

A. Bottom-up
B. Parametric
C. Analogous
D. Three-point

Question 200: Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

A. Cost management plan
B. Quality management plan
C. Communications management plan
D. Risk management plan