Question 161: In a typical project, project managers spend most of their time:

A. Estimating
B. Scheduling
C. Controlling
D. Communicating

Question 162: When closing a project or phase, part of the process may require the use of which type of analysis?

A. Reserve analysis
B. Regression analysis
C. Document analysis
D. Product analysis

Question 163: The scope management plan and scope baseline are contained in:

A. organizational process assets
B. a requirements traceability matrix
C. the project charter
D. the project management plan

Question 164: Which type of organizational structure is displayed in the diagram provided?

A. Balanced matrix
B. Projectized
C. Strong matrix
D. Functional

Question 165: Outputs of the Control Communications process include:

A. expert judgment and change requests.
B. work performance information and change requests.
C. organizational process asset updates and an issue log.
D. project management plan updates and an issue log.

Question 166: In the Plan Procurement Management process, which source selection criteria analyzes if the seller’s proposed technical methodologies, techniques, solutions, and services meet the procurement documents requirements?

A. Technical approach
B. Technical capability
C. Business size and type
D. Production capacity and interest

Question 167: Which element does a project charter contain?

A. Management reserves
B. Work breakdown structure
C. Stakeholder list
D. Stakeholder register

Question 168: The following is a network diagram for a project.

What is the critical path for the project?

A. A-B-C-F-G-I
B. A-B-C-F-H-I
C. A-D-E-F-G-I
D. A-D-E-F-H-I

Question 169: The following is a network diagram for a project.

The free float for Activity H is how many days?

A. 4
B. 5
C. 10
D. 11

Question 170: The most appropriate project life cycle model for an environment with a high level of change and extensive stakeholder involvement in projects is:

A. adaptive
B. reflexive
C. predictive
D. iterative