Over 600 PMI Certified Associate in Project Management (CAPM) Exam Questions and Answers

Question 141: The chart below is an example of a:

A. Responsibility assignment matrix (RAM)
B. Work breakdown structure (WBS)
C. RACI chart
D. Requirements traceability matrix

Question 142: Which Perform Quality Assurance tool or technique is used to identify a problem, discover the underlying causes that lead to it, and develop preventative actions?

A. Inspection
B. Quality audits
C. Design of experiments
D. Root cause analysis

Question 143: In which phase of team building activities do team members begin to work together and adjust their work habits and behavior to support the team?

A. Performing
B. Storming
C. Norming
D. Forming

Question 144: Which is an enterprise environmental factor?

A. Marketplace conditions
B. Policies and procedures
C. Project files from previous projects
D. Lessons learned from previous projects

Question 145: Project Stakeholder Management focuses on:

A. project staff assignments
B. project team acquisition
C. managing conflicting interests
D. communication methods

Question 146: The following chart contains information about the tasks in a project.

Based on the chart, what is the cost performance index (CPI) for Task 2?

A. 0.8
B. 1
C. 1.25
D. 1.8

Question 147: The following chart contains information about the tasks in a project.

Based on the chart, what is the schedule performance index (5PI) for Task 4?

A. 0.83
B. 0.9
C. 1.11
D. 1.33

Question 148: Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?

A. Schedule network analysis
B. Reserve analysis
C. Alternative analysis
D. Variance analysis

Question 149: A project’s purpose or justification, measurable project objectives and related success criteria, a summary milestone schedule, and a summary budget are all components of which document?

A. Work breakdown structure
B. Requirements document
C. Project charter
D. Project management plan

Question 150: In the Define Activities process, the schedule management plan is used to:

A. Capture the lessons learned from other projects for comparison.
B. Contain the standard activity list.
C. Document and support the project change requests.
D. Prescribe the level of detail needed to manage the work.