Question 131: When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is an example of a:

A. lead
B. lag
C. mandatory dependency
D. internal dependency

Question 132: Which action is included in the Control Costs process?

A. Identify how the project costs will be planned, structured, and controlled
B. Determine policies, objectives, and responsibilities to satisfy stakeholder needs
C. Develop an approximation of the monetary resources needed to complete project activities
D. Monitor cost performance to isolate and understand variances from the approved cost baseline

Question 133: What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

A. 0.03
B. 0.06
C. 0.10
D. 0.50

Question 134: Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?

A. Control Quality
B. Monitor and Control Project Work
C. Control Scope
D. Perform Integrated Change Control

Question 135: Project management processes ensure the:

A. alignment with organizational strategy
B. efficient means to achieve the project objectives
C. performance of the project team
D. effective flow of the project throughout its life cycle

Question 136: Which items are components of a project management plan?

A. Change management plan, process improvement plan, and scope management plan
B. Agreements, procurement management plan, and work performance information
C. Schedule management plan, project schedule, and resource calendars
D. Scope baseline, project statement of work, and requirements traceability matrix

Question 137: Which project document is updated in the Control Stakeholder Engagement process?

A. Project reports
B. Issue log
C. Lessons learned documentation
D. Work performance information

Question 138: A project manager should communicate to stakeholders about resolved project issues by updating the:

A. project records
B. project reports
C. stakeholder notifications
D. stakeholder register

Question 139: Which Project Time Management process includes bottom-up estimating as a tool or technique?

A. Estimate Activity Resources
B. Sequence Activities
C. Estimate Activity Durations
D. Develop Schedule

Question 140: An input to the Control Quality process is:

A. Activity attributes
B. Quality control measurements
C. Enterprise environmental factors
D. Deliverables