Question 111: Which output of Project Cost Management consists of quantitative assessments of the probable costs required to complete project work?

A. Activity cost estimates
B. Earned value management
C. Cost management plan
D. Cost baseline

Question 112: A stakeholder expresses a need not known to the project manager. The project manager most likely missed a step in which stakeholder management process?

A. Plan Stakeholder Management
B. Identify Stakeholders
C. Manage Stakeholder Engagement
D. Control Stakeholder Engagement

Question 113: Skills necessary for project management such as motivating to provide encouragement; listening actively; persuading a team to perform an action; and summarizing, recapping, and identifying next steps are known as:

A. organizational skills
B. technical skills
C. communication skills
D. hard skills

Question 114: When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

A. improvement
B. program
C. result
D. portfolio

Question 115: The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

A. management
B. response
C. tolerance
D. appetite

Question 116: Which type of graphic is displayed below?

A. Work breakdown structure
B. Context diagram
C. Control chart
D. Pareto diagram

Question 117: Job satisfaction, challenging work, and sufficient financial compensation are values related to which interpersonal skill?

A. Influencing
B. Motivation
C. Negotiation
D. Trust building

Question 118: The following is a network diagram for a project.

The shortest non-critical path for the project is how many days in duration?

A. 10
B. 12
C. 14
D. 16

Question 119: The component of the human resource management plan that includes ways in which team members can obtain certifications that support their ability to benefit the project is known as:

A. recognition and rewards
B. compliance
C. staff acquisition
D. training needs

Question 120: Stakeholders can be identified in later stages of the project because the Identify Stakeholders process should be:

A. Continuous
B. Discrete
C. Regulated
D. Arbitrary