Question 101: Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

A. Verified deliverables.
B. Validated deliverables.
C. Acceptance criteria.
D. Activity resource requirements.

Question 102: An output of the Perform Integrated Change Control process is:

A. Deliverables.
B. Validated changes.
C. The change log.
D. The requirements traceability matrix.

Question 103: During which process does the project team receive bids and proposals?

A. Conduct Procurements
B. Plan Procurements
C. Estimate Costs
D. Control Budget

Question 104: Which output is the approved version of the time-phased project budget?

A. Resource calendar
B. Scope baseline
C. Trend analysis
D. Cost baseline

Question 105: The purpose of the Project Communications Management Knowledge Area is to:

A. Monitor and control communications throughout the entire project life cycle.
B. Maintain an optimal flow of information among all project participants.
C. Develop an appropriate approach for project communications.
D. Ensure timely and appropriate collection of project information.

Question 106: Processes in the Initiating Process Group may be completed at the organizational level and be outside of the project’s:

A. Level of control.
B. Communication channels.
C. Scope.
D. Strategic alignment.

Question 107: At the completion of a project, a report is prepared that details the outcome of the research conducted on a global trend during the project. Which item did this project create?

A. Result
B. Product
C. Service
D. Improvement

Question 108: Through whom do project managers accomplish work?

A. Consultants and stakeholders
B. Stakeholders and functional managers
C. Project team members and consultants
D. Project team members and stakeholders

Question 109: The following is a network diagram for a project.

The free float for Activity E is how many days?

A. 2
B. 3
C. 5
D. 8

Question 110: Specification of both the deliverables and the processes is the focus of:

A. Change control
B. Configuration control
C. Project monitoring and control
D. Issue control